Construction crews work to rebuild the Rialto Beach jetty as seen from across the Quillayute River from LaPush. (Lonnie Archibald)

Construction crews work to rebuild the Rialto Beach jetty as seen from across the Quillayute River from LaPush. (Lonnie Archibald)

Work underway on damaged section of Rialto revetment at La Push

U.S. Army Corps of Engineers estimates that the repairs on the 300-foot-long section of the protective jetty will be finished in about three weeks.

LA PUSH — Work continues on a 300-foot-long damaged section of the Rialto revetment near La Push, with the U.S. Army Corps of Engineers estimating repairs will be completed in about three weeks.

Coastal revetments are sloping structures placed on banks or cliffs that absorb the energy of incoming water in order to prevent erosion. The damaged barrier is essentially a rocky jetty that protects La Push.

A 300-foot-long stretch of the revetment has failed on the west side, according to the Corps, and only the underlying gravel berm remains.

So far, the project is slated to cost about $1.6 million, said Patricia C. Graesser, U.S. Army Corps of Engineers public affairs supervisor for the Greater Seattle area.

The repairs are being conducted by Bruch & Bruch Construction Inc. of Port Angeles, Columbia Granite LLC of Olympia, and SEA Construction LLC of Raymond.

“A crew of three from the Corps is overseeing repairs to the revetment and expect to complete work in the next few weeks,” Graesser said.

It isn’t clear exactly when or how the revetment was damaged, but officials believe winter storms last year were likely the cause, said Bill Dowell, U.S. Army Corp of Engineers spokesperson.

Noticed in spring

The damage was first noticed in late March or early April of this year, he said.

Before construction crews and heavy equipment could access the revetment, a damaged stretch of Mora Road in Olympic National Park — the only access road to the site — needed to be repaired and widened, Graesser said.

A Corps team began widening the road Oct. 14 to allow trucks to haul material to the revetment for the needed repairs.

As of Friday, contractors were delivering stone to the site that will be used to strengthen the barrier, Graesser said.

The 3,000-foot-long revetment was built in 1974 and last rehabilitated after a breach in 1996, Graesser said.

The structure’s crest in the damaged area is between four and six feet lower than the design elevation and adjacent structure elevation, according to the Corps. Given the revetment’s condition, if no action was taken a breach in the damaged area would be highly probable.

Emergency repair efforts were prompted by a series of storms that arrived in the Pacific Northwest beginning Oct. 13, according to Graesser.

If the revetment had been breached during the storms, it could have exposed the Quileute reservation riverward shoreline, Coast Guard Station, training wall and Quileute Marina to direct wave action, Graesser said.

A training wall is an artificial embankment or wall for directing the course of a stream or river, in this case the Quillayute River, which runs to the east of Rialto Beach.

The training wall is not designed to protect the marina or other facilities from wave action and likely would have been destroyed if exposed to ocean waves and debris, Graesser said.

Because the marina is the only safe harbor for 60 miles along the Pacific Ocean, the Corps initiated emergency repairs to the revetment, Graesser said.

“Because of the threat of a breach, we received emergency funding to address the immediate threat,” she said.

“Additional work will still be required after storm season.”

The threat underscores efforts by the Quileute tribe to move much of its community. Much of the reservation — including the existing school site adjacent to First Beach, the Quileute Tribal Center, the Quileute Senior Center and many homes — is directly in the path of possible tsunamis or flooding from the Quillayute River, according to the Quileute tribe.

________

Features Editor Chris McDaniel can be reached at 360-452-2345, ext. 56650, or at cmcdaniel@peninsuladailynews.com.

Reporter Jesse Major contributed to this report.

Road closed signs are set up at the Mora Ranger Station on the Mora Road as the road from that point on to Rialto Beach is closed due to work being done on the rialto Beach jetty. (Lonnie Archibald)

Road closed signs are set up at the Mora Ranger Station on the Mora Road as the road from that point on to Rialto Beach is closed due to work being done on the rialto Beach jetty. (Lonnie Archibald)

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading