The site of the former Peninsula Plywood mill in Port Angeles sits cleared and vacant

The site of the former Peninsula Plywood mill in Port Angeles sits cleared and vacant

WEEKEND REWIND: Port of Port Angeles approves settlements for millions for plywood mill site cleanup

PORT ANGELES –– Port of Port Angeles commissioners have approved settlements with ExxonMobil and Rayonier Advanced Materials that will reimburse the port’s out-of-pocket costs of cleaning the former 19-acre plywood mill site at 439 Marine Drive.

ExxonMobil will pay $5.5 million and Rayonier $2.2 million as reimbursement to the port for their shares of the costs.

Commissioners took action Monday.

“This final settlement will make the port whole,” said Chris Hartman, director of engineering at the port.

“On top of that, there will be money going back to the insurance carrier for what they have paid.”

The port has paid $8,995,711 for the cleanup costs, of which $6,024,354 has been reimbursed by the port’s insurers.

“No taxpayer money was spent in the end,” said Colleen McAleer, port commissioner. “That’s huge.”

The costs of the cleanup were distributed based on where the pollution came from, Hartman said.

ExxonMobil paid more in the settlement because of the amount of the soil hauled away from the cleanup site that was contaminated with gasoline and diesel.

Rayonier’s share was based on hydraulic oil in the cleanup.

The port also will be returning money to the state Department of Ecology, which provided a $2 million grant early in the process that helped fund the upfront costs of demolishing the mill in 2013.

“Now that we’ve settled with Exxon and Rayonier, we’re able to pay that money back,” Hartman said.

Hartman said cleanup of the site finished in May and that the port will continue to monitor the site.

Starting in the 1920s on filled earth, log yards, paper mills, bulk fuel plants and pipelines, and plywood mills — including KPly and, more recently, the Peninsula Plywood mill that closed in 2011 — occupied the site.

The site has been cleared and inspected for the gasoline, diesel fuel, benzene, heavy oil, hydraulic fluid, toluene and other poisons that had soaked into its soil.

Monitoring wells will be used for long-term monitoring to check groundwater in the area for pollutants.

Because the port opted to pay the upfront costs of the cleanup, Hartman said, the cleanup was able to be finished quickly.

“It’s a very lengthy process,” he said. “We were able to get through the process about as quick as any project I’ve ever had . . . largely due to the port commission being willing to spend the money upfront and seek reimbursement after the fact.”

The port’s attorney, Simon Barnhart, said the cleanup process at the former mill site could be held as an example for other agencies to emulate.

Karen Goschen, executive director of the port, said the port has taken an aggressive position in pursuing the cleanup.

In October 2012, the port signed an order with Ecology to conduct a remedial investigation.

From 2012-15, the port’s environmental consultant prepared work plans, conducted field investigations and prepared a draft cleanup action plan.

In May 2015, Ecology approved the cleanup actions, which required excavation of polluted soils, injections of bio-amendments to groundwater and long-term monitoring of soil and groundwater.

Goschen said that in March, the port was able to work out tentative terms with ExxonMobil and then later Rayonier on the cleanup.

With the cleanup and settlement finished, port officials now are looking toward developing a marine industrial park at the site.

Exactly when it would be built is still up in the air, Hartman said.

The industrial park would be an expansion of what is already on Marine Drive, he said, and would be similar to the work Westport and Platypus Marine are doing.

Hartman said the port is working with a consultant to do master planning for the site and is meeting with local shipbuilders and repair companies to gather information about what kind of infrastructure is needed.

“We’d be willing to start construction as soon as we get some tenant commitment on wanting to have a long-term lease on site,” he said. “We have to be wise with the dollars we spend.

“We have to get a broad base of input from ship repair companies and boatbuilders and make sure we get the highest return on investment.”

________

Reporter Jesse Major can be reached at 360-452-2345, ext. 56250, or at jmajor@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading