Water Street sewer repair project underway

Work expected to continue until mid-May

PORT TOWNSEND — Construction on Port Townsend’s $3.2 million Water Street sewer replacement project has begun and is expected to continue through mid-May.

Originally planned to begin on Jan. 10, the project was delayed until Monday in the contracting process, said Andre Harper, a city project manager.

“Once the general contractor, ACI, was contracted the project, they had to assess their workload, their mobilization process, and after assessing all those things, they needed to push back the schedule for a couple weeks, which has no overall impact to the schedule,” Harper said.

Work will take place between 7 a.m. and 6 p.m., according to a press release.

The project is planned to stretch a section of Water Street from several hundred feet southwest of the ferry terminal intersection to the corner of Water Street and Gaines Street.

The project has a lot of moving parts, Harper said in a November interview.

The repair and replacement project will involve two main sub-projects, Harper said. One will extend the Monroe lift force mainline by 1,850 feet, using a method called horizontal directional drilling (HDD).

The other will involve retrofitting about 1,830 feet of pre-existing asbestos concrete (AC) pipe by “sliplining” a smaller pipe into the existing pipe.

Both projects will use high-density polyethylene (HDPE), Harper said.

Harper said that, to his knowledge, pipe slated for replacement and repair is original to the 1966 installation of the sewer system.

The Water Street sewer main serves most of downtown Port Townsend and some of uptown, Harper said in November.

“The sewer main along Water Street is one of the main arteries that, after collection through the Monroe lift station, feeds back to our wastewater treatment plant via the Gaines Street pump station,” Harper said.

Costs

Beyond the $2.3 million contract with ACI, monies spent have gone toward consulting, design work, administration work and archeological site-monitoring, Harper said.

“One of the key cost adders that was unexpected was the emergency repair work that was performed back in, I think it was August 2024, when we had a pipe failure at the intersection,” Harper said. “We did not anticipate that cost.”

In addition to the pipe failure near the intersection of Water Street and the ferry terminal, a section of pipe close to Gaines Street failed in December 2022.

Early progress

Progress has occurred since Monday, Harper said.

“Aside from mobilization and traffic control cordoning-off, we’ve also had contractor training of archeological unintended finds,” Harper said.

An archaeologist was onsite from Willamette Cultural Resources, Harper said.

“What was done (Monday) was they dug the first pit for horizontal directional drilling,” Harper said. “We are expecting that the additional three pits along the alignment will be dug over the course of this week, then the drillers will come in and do the HDD, horizontal directional drilling.”

Harper met with the management team at the ferry terminal on Tuesday.

“We talked about keeping the aisles open, both inbound and outbound, for the ferry terminal,” Harper said. “We’re coordinating with the WSDOT.”

Corridor considerations

“The plan is to reduce the traffic to one lane in each direction with flaggers,” Harper said.

Harper said there is a possibility of detours, but they are not planned.

On the bluff side of the street, a lane will be closed and the bike lane will be closed with open pits for sewer connections. Pits will be closed during non-construction hours, according to a city press release.

Business and residential parking will be open throughout the construction area, barring the angled street parking behind the Triangle building on Water Street, between Gaines Street and state Highway 20. The area will be used for equipment storage and material staging, Harper said.

The press release said the first part of the project will include asphalt and construction sawcutting, which will generate construction noise during work hours.

The city council authorized city manager John Mauro to enter the city into a contract with ACI Inc. in November.

For more information and updates on the project, visit the city’s dedicated project webpage, https://cityofpt.us/engagept/page/water-street-sewer-replacement-project-0.

________

Reporter Elijah Sussman can be reached by email at elijah.sussman@sequimgazette.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading