Upper Sims Way project under budget, says city manager

PORT TOWNSEND — The Upper Sims Way renovation project came in a little more than $1 million under budget, said City Manager David Timmons on Thursday.

Timmons also corrected a figure reported since last September for the proposed cost of the project: $7.1 million.

The Sims Way upgrade in Port Townsend was never expected to cost $7.1 million, Timmons said.

The budget was $5.5 million.

The actual cost of the project, now that it is completed: $4,493,206.

Where did the $7.1 million figure come from?

Go to the city’s Upper Sims Way Improvement Project website at http://tinyurl.com/2fvvnby, which was put up in September 2009.

Add up the line of figures describing funding sources for the project. That comes to $5,540,000.

Just above the line of figures is a note that says that Port Townsend received an additional $1.6 million in federal funds “which makes the project fully funded.”

Add that to the $5.5 million figure and the sum is $7,140,000.

But the $1.6 million figure was included in the $2,100,000 figure cited as coming from federal stimulus funds, and so should not have been added to the original budget, the city manager said.

Why did Timmons wait until Tuesday, when he sent out an e-mail saying that the $7.1 million was an “urban myth,” to correct it?

‘Didn’t pay attention’

“We’ve been so busy dealing with the issue [the renovation project itself] that we never paid attention to the reporting error until we started having all these criticisms coming out about the expense,” Timmons said Thursday.

“We had some people saying it was a waste of tax dollars,” he explained.

“I didn’t pay attention to this error until I was asked to explain.”

The actual cost of the project so far has been $4,443,206, and another $50,000 in bills is outstanding, Timmons said in his Tuesday e-mail.

That means the total cost will be $4,493,206.

That includes design and permitting ($811,327), right-of-way acquisition ($128,492), construction ($3,123,387), engineering ($380,000) and the $50,000 outstanding.

Under budget

What caused the project to come in under the budget planned in 2009?

“There were several factors there that came into play,” Timmons said.

“We just got a very good price,” from Seton Construction. Inc., a Port Townsend-based business.

The Port Townsend-based company’s base bid for construction was $2.6 million but with additional work in and around Sims, it was over $3 million, Timmons said.

“Being local helped make them more competitive,” Timmons said, because out-of-town companies would have higher expenses in bringing employees and equipment to town.

Other expenses included undergrounding utilities, cleanup and remediation, design and permitting, environmental testing and environmental mitigation in constructing wetlands, Timmons said.

Of the $1 million not used for the renovation, $500,000 is in Jefferson County Community Investment funds.

These are sales tax dollars collected in Port Townsend and throughout Jefferson County. The county administers the funds for economic development. The purpose is to support infrastructure, Timmons said.

“We held back the $500,000 of county funds because if we had used that money we would have had to refund the federal stimulus funds,” according to federal rules, Timmons said.

The city may also lose some $500,000 in federal stimulus funds, since it wasn’t used for the project, Timmons said.

City officials won’t know the status of that money until federal auditors finish their work, which is going on now and which will continue for the next couple of months.

“Once we reconcile and close the books, it may go back to the federal programs,” Timmons said.

After auditors have finished their work, city officials plan to return to the county to request that the $500,000 in county community investment funds now go to the Howard Street extension to Discovery Road, Timmons said.

Howard Street project

The Howard Street project, which is expected to cost $5,175,000 for two phases of the extension, is intended to create an alternate route into the city and open a new retail area, Planning Director Rick Sepler has said.

Preliminary designs are completed, Timmons said, and bids could be requested this fall — if the city resolves a wetlands mitigation issue and receives funding, Timmons said.

A new round of federal stimulus funding is expected in August.

If all goes well with funding and permits, construction on the Howard Street extension could begin next spring, Timmons said.

“The nice thing there is, we have no businesses that will be interrupted because it’s currently an undeveloped stretch,” the city manager said.

________

Managing Editor/News Leah Leach can be reached at 360-417-3531 or leah.leach@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading