Truss span sections installed for Dungeness River Bridge project

SEQUIM — Construction crews were busy Thursday morning preparing the second steel truss span section for installation on the western trestle of the Dungeness River Bridge.

The first span section was dropped into place Wednesday.

The $1.53 million construction project at Railroad Bridge Park, 2151 W. Hendrickson Road, is expected to be completed within the next two months.

The Jamestown S’Klallam tribe owns both the park and the bridge, and is funding the project with grants, insurance money and other sources.

Nordland Construction, headquartered in Port Townsend, has been contracted by the tribe to complete the project using design and engineering schematics by Otak of Portland, Ore.

The new 750-foot-trestle replaces a 570-foot-long wooden trestle damaged by a storm in February. The damaged trestle has been demolished and removed.

The bridge itself is undamaged, but traffic over it has been closed since February because the old trestle connecting it to the west bank was unsafe.

That blocked use of a portion of the Olympic Discovery Trail, which will eventually span the North Olympic Peninsula from Port Townsend to LaPush.

The new trestle began arriving last month in prefabricated 60-foot-long, 9-foot-deep sections.

The steel sections are manufactured by Wheeler Lumber LLC — a Minnesota firm that specializes in metal, fiberglass and timber prefabricated bridges — and transported to Sequim on flatbed trucks.

Crews are bolting the sections together to create four 182-foot-long sections. A fifth 22-foot-long section will be placed in the middle.

Once the old trestle was completely removed, crews began driving steel pilings that will support the new trestle into the ground at four locations.

The old trestle previously was propped up in 38 areas by five creosote poles in each location. The depth of the pilings varied from 6 feet to 25 feet.

Contractors finished removing the old creosote-covered poles in October, a task that began in August.

The replacement trestle will allow logs and migrating salmon to pass beneath without hindrance by reducing the number of support beams needed to prop up the walkway.

After the steel pilings were driven, concrete piers were then placed on top of the pilings to hold up the trestle.

A concrete pier beneath the existing Howe Truss bridge will support the new trestle where the two structures connect.

The final phase is to lower a walkway onto the piers with two massive cranes.

Members of the 10-man crew must work together in tightly controlled choreography to lower the spans, Robert Bufford, foreman of Nordland Construction, said while preparing the second truss section Wednesday.

“There is a lot of coordination with the cranes being set up,” he said.

“You take one end and put it on a truck and put the other end on a dolly and travel down” to the river from the staging area, he said.

Mud at the site created by recent rains has not hindered the operation, he said.

Funding for the replacement project came from a state Recreation and Conservation Office Salmon Recovery Funding Board grant.

Several other sources of funding also will be used, including tribal insurance coverage payments, tribal transportation funding, a Bureau of Indian Affairs grant, a state Floodplains by Design grant and a contribution from the Peninsula Trails Coalition.

Additionally, a First Federal Community Foundation grant of $100,000 will fund the re-decking of the Howe truss bridge portion of the crossing.

When the trestle was damaged last February, engineers assessed the older wooden structure. The tribe elected to replace, not fix, the trestle section.

The design and engineering work was funded by a $172,000 grant from the state Salmon Recovery Fund Board.

________

Sequim-Dungeness Valley Editor Chris McDaniel can be reached at 360-681-2390, ext. 5052, or cmcdaniel@peninsuladailynews.com.

More in News

U.S. Rep. Emily Randall.
US Rep. Randall speaks on House floor about insurance

Example of fictional family shows premium increase of more than 1,000 percent

Spending patterns led to pool audit

Office identifies $33K in unsupported payments

Comments oppose plan against Port Townsend zoning changes

Option would increase maximum limit on units per 40,000 square feet

x
Sequim program uses grant for utilities, rent

Community support through Peninsula Home Fund gives $10,000 to organization

Firefighters Tyler Gage and Tatiana Hyldahl check out the light connections on the 1956 fire truck that will travel the streets of Port Angeles during the 41st Operation Candy Cane beginning Monday. Santa and his helpers will pass out candy canes to those who donate food items or cash. The runs will begin at 5:30 p.m. and include the following areas: Monday, west of I street and M street; Tuesday, I and L streets to C street; Wednesday, C Street to Lincoln Street; Thursday, Chase Street to Chambers Street; Friday, Jones Street to Golf Course Road; Dec. 13, above Lauridsen Boulevard. It will be stationary from 5:30 p.m. to 7 p.m. on Dec. 14 at the Port Angeles Grocery Outlet and during the same time on Dec. 15 at Lower Elwha Food and Fuel. (Dave Logan/for Peninsula Daily News)
Operation Candy Cane

Firefighters Tyler Gage and Tatiana Hyldahl check out the light connections on… Continue reading

Online survey launched for Sequim parks access

The city of Sequim has launched an online survey to… Continue reading

Crews work to remove metal siding on the north side of Field Arts & Events Hall on Thursday in Port Angeles. The siding is being removed so it can be replaced. (Dave Logan/for Peninsula Daily News)
Siding to be replaced

Crews work to remove metal siding on the north side of Field… Continue reading

Tsunami study provides advice

Results to be discussed on Jan. 20 at Field Hall

Chef Arran Stark speaks with attendees as they eat ratatouille — mixed roasted vegetables and roasted delicata squash — that he prepared in his cooking with vegetables class. (Elijah Sussman/Peninsula Daily News)
Nonprofit school is cooking at fairgrounds

Remaining lectures to cover how to prepare salmon and chicken

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects