Towne Road is now finished

Overview highlights years-long project

PORT ANGELES — After 15 years and multiple variations of the project, Towne Road — which runs along the eastern edge of the Dungeness River near Sequim — is complete at a cost about $22.5 million.

Clallam County Administrator Todd Mielke presented an overview Monday before the three county commissioners, highlighting how the project changed since it was first in the transportation improvement plan in the early 2000s to how it was finalized and reopened last October.

It eventually morphed into three separate projects: Restoring the Dungeness floodplain, including the relocation of the lower levee, plus the relocation of the upper levee known as the River’s Edge project, and the relocation of Towne Road, restoring a piece of the county’s transportation network and providing a designated pedestrian and bicycle path for recreation.

“It’s hard to keep track of that, and it’s great start for our other multidimensional, multiyear projects,” commissioner Randy Johnson said of the overview. “Hopefully this is the first step in what I consider the right direction.”

Mielke, who was hired in August 2023, said he’s gone through many documents and posted the project on his whiteboard to get familiar with all of its elements and funding sources, the vast majority of which came from grants from the state Department of Ecology, the state Recreation and Conservation Office and the U.S. Fish & Wildlife Service.

Out of the total, Clallam County contributed about $2 million.

“I kind of stepped in over the last 15 months,” he told commissioners. “The good part is, it was a different set of eyes. The bad part is figuring out how to connect the dots.”

The original discussion in the early 2000s included a $1.2 million project to resurface and potentially reconstruct the road, Mielke said.

By 2008, the focus switched to realigning the levees and restoring the wetlands in the lower Dungeness floodplain.

“The original levee was nearing the end of its design life and provided a reduced level of protection for the community against flooding,” Mielke wrote in his presentation. “It was built close to the Dungeness River, and winter flood flows in this reach of the river could be rapid enough to result in degraded fish habitat, impacting salmon runs.”

Restoring the lower Dungeness floodplain was the most complex and the most expensive, Mielke said.

“While the state was the primary funder, the project was initially managed and coordinated by the (U.S. Army) Corps of Engineers, from 2009 through 2016,” he wrote in his presentation. “This project was anticipated to have multiple phases and required coordination between federal, state, county and tribal governments. It was considered highly complex and would cost millions to complete.”

Separately, the realignment of the upper levee, or the River’s Edge project, became possible in 2018, when landowners upstream chose to sell their property, Mielke said.

The Jamestown S’Klallam Tribe took the lead on the River’s Edge project, with permitting through the Corps of Engineers, he added.

Mielke said there wasn’t just one budget for the combined projects. Instead, all three had their own funding amounts and sources, and each major phase had dedicated funding that could only be used for specific purposes. For example, the lower Dungeness floodplain had nine separate grants, and each had its own budget and deliverables.

In 2016, after preferred alternatives were developed, the Corps of Engineers withdrew as the lead for the lower Dungeness floodplain restoration project, and Clallam County stepped forward with an effort coordinated between its Department of Community Development and its Public Works department.

Just before construction began, however, the COVID-19 pandemic hit.

“Contractors and engineering firms that would normally be available to provide professional services, cost estimates and bids on work were shut down,” Mielke wrote in the presentation. “Many government employees necessary to process permit reviews and approvals were no longer working in agency offices.”

During the shutdown, the county successfully applied for a $2.8 million floodplain construction grant from the state Recreation and Conservation office, adding to a series of grants from multiple sources.

Overall, the county had $5.1 million in planning, predesign and design grants, a $575,000 grant for land acquisition and relocation of buildings and infrastructure, more than $8 million in wetland and floodplain restoration grants, and $8.8 million in construction grants, Mielke said.

“The relocation of the levees has greatly enhanced protections against high winter flows and the potential for flooding,” Mielke wrote in the presentation. “The expansion and restoration of the floodplain, and reconnecting the river to more than 175 acres of floodplain, has improved wildlife habitat – and that presence of wildlife continues to grow.

“The projects have slowed the flow of the Dungeness River, resulting in better salmon and fish habitat. The local community is now using the shore of the river near the Old Schoolhouse more than ever as a recreational location to enjoy the outdoors since access to the river has improved.”

________

Editor Brian McLean can be reached at 360-417-3531 or by email at brian.mclean@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading