A screen grab from the remains of Glines Canyon Dam on Saturday morning. Olympic National Park

A screen grab from the remains of Glines Canyon Dam on Saturday morning. Olympic National Park

SUNDAY — Demolition blast expected at Glines Canyon Dam

OLYMPIC NATIONAL PARK — Crews on the $325 million Elwha River dam-removal and restoration project expect the next chunk of Glines Canyon Dam to be blown out sometime today, according to the project superintendent.

Aaron Jenkins with Barnard Construction, the Montana-based firm contracted with the National Park Service on the dam removal, said Friday his crews’ goal is to blast about 1,250 cubic yards of concrete from the remnant of Glines Canyon Dam between 1 p.m. and 5 p.m. today.

The time frame is just an estimate, Jenkins cautioned, since high winds or equipment malfunctions could delay the “shot,” as the demolition explosions are called.

The blast, when it happens, will follow a little more than a week of work in which crews drilled holes in the remaining 55 feet of Glines Canyon Dam along the Elwha River to place explosives, Olympic National Park spokeswoman Barb Maynes said Friday.

Down to 35 feet

The roughly 2,000 pounds of explosives are expected to reduce most of the west side of the dam remnant to 35 feet above the riverbed, Maynes said.

The drilling work, begun almost immediately after the last blast Jan. 15, has taken a bit longer than expected because crews have had to deal with steel reinforcement within the concrete in addition to the concrete itself, Maynes explained.

“That [has been] just taking additional time because steel behaves differently than concrete does,” Maynes said.

Maynes said complete dam removal is still expected by this September.

“More drilling, shots, and rubble excavation are scheduled after this shot to fully remove Glines Canyon Dam, hopefully before the next fish window later this [May],” Jenkins said in an email.

The new hole in Glines Canyon Dam is not expected to increase river flows, Maynes said, since there is no more accumulated water behind the dam to come surging through the new opening.

“There’s not any extra water that will be released,” Maynes said.

“The river will be flowing over a waterfall that’s not quite as high.”

More sediment

The blast will likely result in more sediment gradually coming down the river as it begins to cut more deeply into the material built up behind the dam, Maynes said.

“It will be carrying more sediment as it cuts further down into the reservoir bed,” she said, adding that it won’t be a pulse of sediment as has been seen earlier in the dam-removal process.

“In terms of having impact to the salmon populations, they really aren’t in the river at this point,” Maynes added.

Blasting resumed in October after a more than a yearlong hiatus due to river-borne sediment clogging the national park-managed Elwha Water Treatment Plant.

Repairs and improvements to the treatment plant started early last year and completed in October have allowed dam removal to continue, Maynes said.

“And [the plant] is functioning very well,” she said.

The once-210-foot-tall Glines Canyon Dam is being removed via controlled explosions as part of the largest dam-removal project in U.S. history.

Dam removal began in September 2011, and the century-old, 108-foot-tall Elwha Dam was completely gone by March 2012.

The dams were built in the early 1900s without fish passages, barring the Elwha River’s legendary salmon populations from reach much of their spawning habitat.

________

Reporter Jeremy Schwartz can be reached at 360-452-2345, ext. 5074, or at jschwartz@peninsuladailynews.com.

More in News

Crews work to remove metal siding on the north side of Field Arts & Events Hall on Thursday in Port Angeles. The siding is being removed so it can be replaced. (Dave Logan/for Peninsula Daily News)
Siding to be replaced

Crews work to remove metal siding on the north side of Field… Continue reading

Tsunami study provides advice

Results to be discussed on Jan. 20 at Field Hall

Chef Arran Stark speaks with attendees as they eat ratatouille — mixed roasted vegetables and roasted delicata squash — that he prepared in his cooking with vegetables class. (Elijah Sussman/Peninsula Daily News)
Nonprofit school is cooking at fairgrounds

Remaining lectures to cover how to prepare salmon and chicken

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park