State pollution board ruling sides with Nippon Paper Industries USA biomass project in Port Angeles

PORT ANGELES — The state Pollution Control Hearings Board has sided with Nippon Paper Industries USA in a challenge from several groups, including PT AirWatchers, to its $71 million biomass energy project.

Environmental groups are fighting biomass expansion projects at the Nippon mill in Port Angeles and the Port Townsend Paper Corp. mill.

In June, seven of the groups appealed a construction permit for Nippon that was granted by the Olympic Region Clean Air Agency, alleging it was based on faulty data.

In a summary judgment, the board ruled Jan. 4 that the groups failed to prove that the emissions calculations used by the agency were incorrect.

“This ruling substantiates the excellent work that Nippon did to make sure that the biomass boiler project had the best environmental controls available,” said Harold Norlund, mill manager, in a written statement.

Darlene Schanfald, a spokeswoman for the Olympic Environmental Council, one of the groups that joined the appeal, said the groups are considering their next option for appeal: Thurston County Superior Court.

In addition to PT AirWatchers and the Olympic Environmental Council, groups who joined the appeal are Protect the Peninsula’s Future, No Biomass Burn, the North Olympic Group of the Sierra Club, World Temperate Rainforest Network and the Olympic Forest Coalition.

The groups have until Feb. 3 to file an appeal, Schanfald said.

Port Townsend project

Also in June, Port Townsend AirWatchers, No Biomass Burn, the Olympic Environmental Council, the Western Temperate Rainforest Network and the Olympic Forest Coalition filed an appeal of Port Townsend Paper’s $55 million biomass project to Thurston County Superior Court.

That appeal challenges a review by the Pollution Control Hearings Board that sided with the mill and its biomass project that could produce up to 25 megawatts of electricity.

The company could then sell credits for the electrical power.

A trial is set for March 23.

The expansion of Nippon’s biomass boiler, expected to be finished in April 2013, would produce up to 20 megawatts of electricity by burning wood waste from logging sites and sawmills.

Schanfald said the groups still feel they have the “merits of the case,” despite the loss of the appeal of the Nippon project.

“We have a fabulous expert air witness,” she said, referring to Bill Powers, an engineer from San Diego who testified for them.

“If the Pollution Control Hearings Board didn’t pay attention to what he provided them, we wonder if the board just doesn’t understand these cases and doesn’t want to handle them.”

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading