Steve Roark, assistant regional administrator for the state Department of Transportation, speaks about the current state of the U.S. Highway 101 bridge over the Elwha River and plans to replace it during a special presentation to the Port Angeles City Council on Tuesday. (Keith Thorpe/Peninsula Daily News)

Steve Roark, assistant regional administrator for the state Department of Transportation, speaks about the current state of the U.S. Highway 101 bridge over the Elwha River and plans to replace it during a special presentation to the Port Angeles City Council on Tuesday. (Keith Thorpe/Peninsula Daily News)

State engineers update communities on new Elwha River bridge plan

Construction contract being prepared

PORT ANGELES — Crews will break ground on a new bridge over the Elwha River this summer to provide a safer crossing for U.S. Highway 101 once it is completed in 2021, the Port Angeles City Council heard this week.

State Department of Transportation (DOT) engineers are “just about pencils down” on designing the $32.5 million project, a DOT official said Tuesday.

“We’re preparing a construction contract right now,” said Steve Roark, DOT assistant regional administrator.

“We’re pretty stoked to get this rolling.”

The three-span concrete bridge will be built to the north of the existing bridge. The old bridge will continue to serve highway traffic during construction.

The new two-lane bridge will have a more gentle approach on the east side of the river and a wider road surface with 12-foot lanes and eight-foot shoulders on both sides.

Olympic Hot Springs Road will get a new intersection east of the bridge with better sight lines, illumination and dedicated turn lanes from the highway, Roark said.

Before construction, DOT must obtain a National Environmental Policy Act, or NEPA, permit and secure a highway easement deed from the federal government.

“We’ll go to construction once we have a letter of consent from the Department of Interior and Olympic National Park,” Roark told the City Council and dozens of citizens who attended the special meeting.

“Our plan is to be under contact this summer.”

DOT is required by statute to award a construction contract to the lowest responsible bidder.

Construction is scheduled to take 18 to 24 months, after which time traffic will be shifted onto the new bridge.

“We have to sink 10-foot diameter shafts down about 60 feet into the river bed to make this bridge meet seismic standards,” Roark said.

Built in 1926, the existing bridge was undercut by changes to the Elwha River after removal of the Elwha and Glines Canyon dams from 2011 to 2014. The river scoured its channel after dam removal, exposing the footings of the bridge piers.

DOT secured the bridge from further erosion by placing nearly 5,000 tons of boulders around the piers.

“It’s still safe,” Roark said. “The bridge is stable, and we’re keeping it stable through some of the emergency efforts we’ve done.”

The 388-foot-long old bridge is being monitored with tilt meters, crack meters and visual checks.

“We have a lot of data collection going on out there,” Roark said of the real time measurements.

“So we’re watching it, and our maintenance folks are out there on a regular basis, and we have, as you’re all aware, regular bridge inspections.”

The next bridge inspection is scheduled for Feb. 19. Drivers can expect one-way, alternating traffic at the Elwha Bridge during that morning.

State Reps. Mike Chapman, D-Port Angeles and Steve Tharinger, D-Port Townsend and state Sen. Kevin Van de Wege, D-Sequim, helped secure state funding for the new Elwha River bridge in the 2018 legislative session.

The new span will be 502-feet long and 40-feet wide. It will have room for Clallam Transit bus stops and a parking area for river access.

When asked if the new bridge would withstand further scouring from the Elwha River, Roark said the piers would be sunk deep into bedrock.

“This river is going to move around,” Roark said.

“The river will be lower, but we’re very confident we’re building a bridge that will not scour.”

Roark and other DOT officials were scheduled to deliver similar updates on the Elwha River bridge project to West End officials and the Forks Chamber of Commerce on Wednesday.

DOT has a dedicated web page for the Elwha River bridge project at www.ElwhaRiverBridge.com.

Meanwhile, Roark announced that DOT will replace three fish culverts on U.S. Highway 101 in West Jefferson County and North Grays Harbor County under one contract this summer.

Motorists can expect one-way alternating traffic while the Steamboat, Fisher and Harlow Creek culverts are replaced with larger fish passages.

“There’s a lot of fish barriers on the Peninsula, so this is going to be a recurring theme year after year in Jefferson and Clallam and other counties,” Roark said.

________

Reporter Rob Ollikainen can be reached at 360-452-2345, ext. 56450, or at rollikainen@peninsula dailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading