State allocation fuels Port Hadlock Sewer Project

Dean: No public vote planned since Local Improvement District not needed

Jefferson County Commissioner Kate Dean.

Jefferson County Commissioner Kate Dean.

PORT HADLOCK — After more than 15 years of off-and-on discussions and planning, the Port Hadlock Sewer Project is closer than ever to coming to fruition now that Jefferson County has received word it will receive more than $20 million from the state for the facility.

The county was notified Monday that the state Legislature awarded the project $20.175 million from federal relief and infrastructure funding provided to the state to allocate.

The estimated cost to bring the sewer to the Phase 1 commercial core area of Port Hadlock is $23.6 million.

The county received $1.422 million from the state last year for the project’s design, leaving about $2 million needed to fully fund the project, said Monte Reinders, county public works director, in a press release.

The county is seeking other funding sources to cover the remaining costs, including grants from the state Department of Ecology, the U.S. Economic Development Administration and others, Reinders said.

“I’m confident we can close that gap now,” he said.

The core area of Port Hadlock includes lower Hadlock and the Old Alcohol Plant.

Because of the funding from the state, the county will not need to form a Local Improvement District (LID) and the sewer project will not go to a public vote, said county Commission Chair Kate Dean.

“The project is going to be much more affordable with this level of subsidy, so an LID does not feel necessary,” Dean said. “LIDs and things like bonds are really the only time that there is a vote on infrastructure projects.

“Infrastructure projects are very much in the purview of jurisdictions like Jefferson County. We will not be going out for a vote on this project. That has never been considered other than a vote for an LID.”

Even if it was needed, an LID wouldn’t be a vote of the public, only people within the core area, she added.

Construction on the sewer is expected to begin at the end of 2022 or the beginning of 2023, Reinders said.

Planning for the Port Hadlock Urban Growth Area (UGA) — including its sewer — has been under way since 1998 with public involvement at each phase, county officials said.

The UGA was formally designated in 2002 to open the area to create more jobs, additional services and affordable housing, Reinders said.

In 2017, 70 percent of property owners in the commercial core approached the county with renewed interest in seeing the sewer project completed.

County commissioners have since been actively working with legislators representing the North Olympic Peninsula, including Rep. Steve Tharinger, who chairs the House Capital Budget Committee, to get funding included in the state’s capital budget, Reinders said.

“We are extremely grateful for Rep. Tharinger’s work on behalf of Jefferson County and this project,” Dean said. “Funding at this level will allow for Port Hadlock property owners in the core area to hook up to sewer at an affordable rate.

“I’m excited to see more economic opportunity and multifamily housing and put density where it belongs — in the urban growth area.”

Tharinger hopes the funding will help the project move forward.

“It’s an important project,” he said. “I think the county, with added funds, can finish the project.

“I think it really helps complete that effort.”

Not enough

Quilcene resident Pamela Roberts, communications specialist for the Concerned Residents of Port Hadlock (CRPH) — a group that opposes the sewer system — doesn’t think the funds will accomplish what the county says they will. She quoted earlier plans on the project estimating the total cost to be more than $100 million over 20 years.

“This entire project will cost well over $120 million dollars so the state’s $20 million dollar grant is but a drop in that huge bucket,” she said in an email Monday night. “The community does not want this boondoggle strapped around their necks.

“Most of these residents are already cash strapped just to keep roofs over their heads.”

The county does not plan to expand the sewer past the core area and has scaled down the project from that initial estimate, Dean said Tuesday, adding that the new funding will allow the project to move forward and be completed.

The estimated cost of $23.6 million is expected to cover the cost of installing the modular treatment plant that utilizes membrane bioreactor technology to treat wastewater to “Class A” reclaimed water standards — required by the state Department of Ecology, Reinders said.

The county does have a 20 percent contingency plan in case costs are slightly more expensive due to labor and material costs once construction begins, Dean said.

The county plans to complete only Phase 1.

If future neighborhoods want to connect to the sewer after it is completed, the county will work with them, but the sewer will not be forced on people who don’t want to connect to it, Dean said.

There have been concerns raised by residential property owners outside the core area.

The county expects to have the design on the project — whose plans have already been approved by the Department of Ecology — to be completed in summer, and the project itself is planned to be completed by the end of 2024, Reinders said.

More specific costs to customers will be announced once the plans are finalized. Hook-up costs to the core area businesses and residents are estimated to be “relatively affordable” due to the majority of capital costs being covered by state and federal funding, Reinders said Tuesday.

The county will develop the sewer ordinance next year. That would establish the connection fees, and “I think the property owners will be mostly pleased with the result,” Reinders said.

________

Jefferson County reporter Zach Jablonski can be reached at 360-385-2335, ext. 5, or at zjablonski@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading