Stages outlined for Fort Worden reopening

PORT TOWNSEND — It’s “almost like wrestling an octopus,” said Fort Worden Public Development Authority’s strategic adviser as he described the process of creating a reopening strategy while battling an ocean of uncertainty.

David Timmons outlined a five-stage process to guide movement toward eventually resuming full operations during a PDA board meeting Wednesday. Port Townsend’s former city manager is advising the quasi-public agency as it navigates the coronavirus epidemic through June 30.

He and PDA Executive Director Dave Robison walked board members and the public through the stages, which were developed to meet three goals: ensuring the Fort Worden campus survives the immediate financial crisis; develop a recovery strategy to reopen PDA operations; and reassess the business model to address COVID-19 mandates.

Response Stage 1: Jan. 1 to March 31 — Identify recoverable costs for work the PDA performed before activities at were fully suspended. The expenses must be in response to the emergency and not otherwise budgeted. PDA staff will review all documentation in support of a request for federal assistance.

PreRecovery Stage 2: April 1 to June 30 — Report the financial status of the PDA and viability to move ahead with the remaining stages.

A restoration of operations analysis needs to be conducted concerning recommendations for services to reopen all or in part beginning July 1.

Recovery Stage 3: July 1 to Dec. 31 — Timmons described Stage 3 as “the heart to bringing the fort back online.” A reopening team will be assembled to develop the strategies for reopening programs and services.

An assessment of future needs also is planned to make the Fort Worden campus more resilient and prepared for future emergency situations.

The PDA hopes the approach meets qualifying standards for federal emergency relief.

Restoration of Operations Stage 4: July 1 to March 31, 2021 — Continue to explore restoring operations that will be influenced by recovery measures. This relates to planning and preparation to bringing back hospitality services (lodging/food), capital activities, partner support and property maintenance.

“We know we will not have fully mitigated items in place for a full reopening,” Timmons said.

Robison said the PDA will spend the next few months focusing on whether an initial reopening can be held later this summer.

“That means sourcing the (personal protective equipment) and other supplies, putting protocols in place for housekeeping, developing campus-wide safe-distancing guidelines, (and determining) restaurant service, and if we can make it safe for our employees and guests. As we move into the fall, we begin looking longer-term.”

Reopen Stage 5: April 1, 2021 — Reaching the goal of a reopened, resilient campus filled with activities free of economic threats and COVID-19-like exposures.

Elements of operations could return sooner if circumstances allow and run concurrently with implementation of recovery measures.

April 1, 2021, is a “no later than” goal to resume “normal” operations based on new-normal standards and recovery measures completed.

The board also heard updates on the PDA’s Makers Square project.

Construction is expected to resume sometime in June as the historic buildings 305, 308 and 324 are repurposed to provide 25,000 square feet of new space to support arts, culture and education programming.

At the same time, the buildings will get a seismic retrofit and an upgrade of utility, sewer, water and electrical services.

Robison also discussed the resumption of camping and glamping activities at the park.

“Our (Jefferson County) Board of Health tied us to Clallam (County) for reopening camping (in Jefferson County’s approved Phase 2 application),” he said. “If we are still linked to the Clallam County recommendation, camping would not be allowed until all of the state is in Phase 2.”

“That really affects our operations,” Robison said. “And sit-down restaurant service won’t be allowed (in Jefferson County) until Kitsap and Clallam counties enter Phase 2.

“It’s important as we consider our recovery plan to stay current with rules coming down from (Gov. Jay) Inslee and the Board of Health.”

________

Sports reporter Michael Carman can be contacted at 360-406-0674 or mcarman@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading