PORT ANGELES — When will the environmental cleanup of Rayonier’s 75 acres of prime waterfront property be completed?

That depends upon determination of how much cleanup must be done.

Planning began in 2000 for the cleanup of dioxins, PCBs and other contaminants left by the company’s pulp mill, which operated on the shore of the Port Angeles Harbor for 68 years before it closed in 1997.

Both Rayonier Inc. and state Department of Ecology officials agree that the property, zoned for heavy industrial use, should be cleaned to accommodate uses to that standard rather than the stricter standards that would be needed for an area zoned for retail or residential development.

But while Rayonier officials say that most contamination on the site has been removed, the state Department of Ecology says the work has just begun.

“We should have a plan to clean up the property ready to go by 2012,” said Rebecca Lawson, Ecology’s regional toxics cleanup program manager.

Ecology and Rayonier are negotiating a final cleanup plan — called an interim action plan — now, Lawson said.

The time it takes to complete the cleanup — which Ecology estimated in 2000 would be finished by 2004 — depends on how much needs to be done.

“One of the reasons that things are not moving more quickly is trying to find the full extent of the [cleanup] site before you do anything,” Lawson said.

At issue is how much soil should be removed from the Rayonier property and the extent of Rayonier’s responsibility for any contamination of surrounding property and Port Angeles Harbor.

The cleanup site, Ecology officials have said, will include any place that Rayonier is found to be responsible for contaminating.

‘Ninety percent or more’

Rayonier estimates “probably 90 percent or more” of contaminated soil — 20,000 tons — has been trucked away, company site manager Warren Snyder said last week.

“It contains most of the contamination,” he said. “There might be a large volume of very low-level contamination left.”

Rayonier has spent about $25 million on the cleanup, said Charles Hood, vice president of corporate affairs.

Rayonier has agreed that it is responsible for contamination of its property and a portion of the Port Angeles Harbor that extends about a mile to the northwest away from the property, Lawson said.

But what Snyder describes as very low-level contaminated soil may need to be removed, Lawson said.

“There are data gaps, and some of those gaps are around the extent of soil contamination, and we need to take a look at the groundwater a little more,” Lawson said.

And Rayonier’s responsibility may extend farther than its property line, she added.

The soil Rayonier has removed “were interim actions done some years ago,” Lawson said.

“The interim actions were good, but we are pushing now to define a study area that we both agree is impacted and try to move forward.”

Ecology conducted testing of property around Port Angeles and took samples from the harbor last year to help the agency determine if the Rayonier mill polluted soil and water far from its site.

Results are expected in the spring.

Hood has said the company has been hesitant about conducting testing beyond its property boundary because it is concerned that it could become liable for contamination it didn’t cause.

Looking for a pattern

A harbor-wide sediment investigation and an off-site soil dioxin study must be completed to determine if Rayonier is responsible for cleaning the harbor and off-site areas, Lawson said.

If toxic pollutants are found on private property, Ecology will look for a pattern that points to Rayonier.

Dioxin can be traced to Rayonier by chemical analysis linking the toxin to chemicals and industrial processes used at Rayonier, along with wind patterns and proximity to the mill, Lawson said.

The agency will examine the substances’ chemical makeup and determine if it can trace a “source pattern” to industrial processes unique to Rayonier, she said.

If so, the identification process could be further enhanced by matching wind direction with the pollutants’ locations.

“We will look at the culmination of information to see if we come up with a pattern,” Lawson said.

New leaders

A year ago, Ecology switched cleanup oversight from its solid waste division to its toxics waste division to speed a slow-moving process, state officials said.

The cleanup is being done under the state Model Toxics Control Act, with oversight from Ecology, the Lower Elwha Klallam tribe and the federal Environmental Protection Agency, all of whom must sign off on the final cleanup.

The EPA judged the site 2 or 3 on a scale of 10 for contamination when it decided not to classify it as a Superfund site in 1999.

Community leaders argued then for cleanup under the auspices of the Model Toxics Control Act instead of the federal Superfund program, believing that a Superfund cleanup would take 10 years, and that the Superfund designation would stigmatize the North Olympic Peninsula.

More information on the cleanup and the off-site study are on Ecology’s Web site at www.ecy.wa.gov under the icon, “toxics,” at the top of the page.

________

Staff writer Paul Gottlieb can be reached at 360-417-3536 or paul.gottlieb@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading