Slipout hole is gone; Hurricane Ridge Road repair on schedule

OLYMPIC NATIONAL PARK — Construction crews repairing Hurricane Ridge Road at the site of a January slipout aren’t working in a hole anymore.

Having removed the water-soaked, fine-grained fill material that had served as the road’s foundation since 1958, workers with Bruch & Bruch Construction Inc. of Port Angeles had, by Wednesday, moved in two-thirds of the rock and gravel that is intended to give the road a firmer perch.

Work on the route to the popular snow recreation area at Hurricane Ridge is on schedule, and the road is expected to be reopened the first week of March — if there are no surprises in the weather, said Barb Maynes, Olympic National Park spokeswoman, Wednesday.

By then, the rest of the road’s foundation is expected to have been built, bringing its level up to the two edges that, after about 100 feet of the road collapsed in a Jan. 18 washout, ended at a gaping hole about a half-mile north of Heart O’ the Hills campground.

“The contractor is taking advantage of the excellent weather,” Maynes said.

The job is contracted at $1.4 million. Federal Highway Administration engineers estimate that the total cost will exceed $2 million when the work is done.

No detour around the slipout was possible, park officials said, and so there has been no paved road access to Hurricane Ridge since the washout.

For several weeks, crews worked in a hole, digging deeper down the 65-foot to pull out sodden dirt, and loading it into trucks that traveled west of Port Angeles to dispose of it.

For the last week to week-and-a half, Maynes said, the trucks that once left the site full and returned empty have been traveling out empty and coming in with rock and gravel to fill the hole and allow crews to build a new road bed.

Crews now work in a smooth dip, with the only hole in evidence being a small trench for a culvert.

The two-lane road, which winds up 17 miles to Hurricane Ridge north of Port Angeles, originally had been built over such fine-grained fill in that spot near Heart O’ the Hills campground that constant rain soaked it beyond its ability to absorb water, Maynes said.

“Rather than allowing the rainwater to flow through, as would happen if there were rocks, the fine-grained sediment absorbed water,” she said.

“It got to a point where it couldn’t absorb any more and just slid away.”

The new, coarser fill material is expected to allow water to run through — and keep the road’s foundation intact.

Crews also replaced the 24-inch culvert at the bottom of the road’s foundation with a 42-inch pipe. The pipe is for a tributary of Ennis Creek, Maynes said.

Although the original culvert hadn’t failed, Maynes said, a larger one was considered an improvement for drainage under the road.

“Now they are reconstructing the slope with rock and gravel to make it more stable,” Maynes said.

________

Managing Editor/News Leah Leach can be reached at 360-417-3531 or leah.leach@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading