Alan Turner of Port Book and News sits on the stairs that ascend the bluff at Laurel Street behind the Conrad Dyar Memorial Fountain in downtown Port Angeles. Keith Thorpe/Peninsula Daily News

Alan Turner of Port Book and News sits on the stairs that ascend the bluff at Laurel Street behind the Conrad Dyar Memorial Fountain in downtown Port Angeles. Keith Thorpe/Peninsula Daily News

Sewer overflow part of six-year program; Laurel Street stairway also discussed

PORT ANGELES — The largest public works effort in the city’s history — a plan to staunch overflow sewage — is included in a 2012-2018 capital facilities and transportation improvement program approved last week by the City Council.

The $41.7 million combined sewer overflow project surpasses the approximately $24 million spent to replace the Eighth Street bridges, the city’s largest public works project to date, Public Works & Utilities Director Glenn Cutler said Friday.

But the CSO project, which has been discussed for years, was approved with little said about it Tuesday night.

Instead, replacement of downtown’s centrally located Laurel Street stairway was the focus of attention before the six council members unanimously approved the $229 million six-year capital facilities and transportation improvement program.

18th in program

The $301,500 stairway project is listed 18th in the program, is not funded and is not slated for construction until 2014.

The six-year plan includes a proposed $27,500 in preliminary work for stairway replacement in 2013.

The stairway’s present condition and ongoing attractiveness to unsavory elements were criticized by some of the evening’s speakers.

“This seems to be the evening for stairs,” quipped interim City Manager Dan McKeen, noting that the K.O. Erickson Trust may install lighting in the area to provide additional security.

“We do not have any additional funding to apply to the stairs at this time,” McKeen said Friday.

The city approved funding to cut away the bluff for the stairway in 1936, according to a July 1936 edition of the Port Angeles Evening News.

The stairway’s steps lead from what is today a motel-dotted, densely populated bluff down to the fountain and mural at Laurel and First streets in the center of downtown.

By Wednesday morning, the city had painted over the graffiti-scrawled back of the mural, and Police Chief Terry Gallagher said Friday that police patrols will increase in the area.

The stairs are “pretty nasty in terms of smell, color, things falling apart, chips, whatever,” one speaker said during the public comment portion of the meeting Tuesday. Her name was unavailable Wednesday.

Port Book and News co-owner Alan Turner, whose store is one doorway away from the mural and stairway, said in a letter to the council that the stairway “attracts drunks and drug dealers who use the area to conduct business, which includes vomiting and urinating in the public space on a regular basis.”

For many tourists, the stairs “are one of the first or last impressions they receive of Port Angeles,” Turner said.

“I suggest the motto should be: ‘Clean them up. Or close them down.’”

‘Scary, filthy, disgusting, embarrassing’

Residents and tourists who have walked the stairs use the words “scary, filthy, disgusting, embarrassing” to describe the experience of walking its steps, said Turner, who parks his car on the bluff and walks the stairway to work.

“It just seems to be more like one of those situations where if we don’t show respect and concern for those things, then no one will show respect for those things,” Turner added Wednesday in an interview.

The city’s $17.3 million waterfront improvement project, slated to begin this summer — also a top priority in the six-year plan — puts the condition of the stairs into perspective, council member Pat Downie said at the meeting.

The stairway is “unsightly” and “not an asset at this point,” Downie said.

Truck route

Speakers at Tuesday’s meeting also said they are concerned the city will establish a truck route from First Street south up Race Street and west down Lauridsen Boulevard.

A $220,000 “Alternative Cross-Town Route Study” is scheduled for 2013 but has not been funded.

It is ranked 25th in the program and is the last project listed for potential 2013 funding.

CSO project

Construction on the combined sewer overflow project will begin later this summer.

The city will use a 5 million-gallon, city-owned tank on the former Rayonier pulp mill site to store untreated sewage and overflow stormwater.

The city is required by the state Department of Ecology to address sewer overflow, which occurs when stormwater floods the city’s sewage system, parts of which were built to carry both, and untreated effluent is dumped into Port Angeles Harbor.

Infiltration of groundwater into dilapidated sewage pipes also is a significant contribution to the problem.

About 32 million gallons of untreated sewage and stormwater overflow on average each year.

The tank’s contents will be treated at the city wastewater-treatment plant before being discharged into Port Angeles Harbor, Cutler said.

The project, which includes laying new pipes from downtown to the tank, will be completed by Dec. 31, 2015, Cutler said.

The city’s 2012-2018 capital improvement plan and transportation improvement program are available at http://tinyurl.com/8a7wwh4.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at paul.gottlieb@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading