Leaders for the Jamestown S’Klallam Tribe anticipate breaking ground on a new sewer system connecting its facilities such as the 7 Cedars Casino to the city of Sequim’s Wastewater Facility. (Matthew Nash/Olympic Peninsula News Group)

Leaders for the Jamestown S’Klallam Tribe anticipate breaking ground on a new sewer system connecting its facilities such as the 7 Cedars Casino to the city of Sequim’s Wastewater Facility. (Matthew Nash/Olympic Peninsula News Group)

Sequim, Jamestown S’Klallam Tribe approve wastewater agreement

SEQUIM — The Jamestown S’Klallam Tribe recently inked a deal to send its wastewater to Sequim, with the water lines to be constructed at about the same time that the tribe begins work on a five-story hotel.

The resort hotel will be between 7 Cedars Casino and the fireworks stand.

Included in the Sequim wastewater connection are 7 Cedars Casino, the Longhouse Market and Deli, the Blyn Fire Station, the tribe’s incoming Justice Center, resort and other existing administrative and business buildings.

Tribal Council Chairman W. Ron Allen said the tribe’s facilities on the north and south campuses in Blyn will connect via new pipes along U.S. Highway 101 to Sequim’s Water Reclamation Facility via Whitefeather Way.

“We’re very excited for the project,” Allen said. “We debated about building our own [wastewater system]. It was an exhaustive process.”

Allen said it creates a dependency on the city, but he and fellow tribal leaders felt it was advantageous because the city has “the staffing and expertise to handle any issues.”

Allen said he anticipates the project breaking ground in February of next year at a cost of about $8.5 million, with funds coming from a 40-year loan from the federal Department of Agriculture.

The city and tribe discussed wastewater options for years, and Sequim city councilors unanimously finalized the interlocal agreement Monday, Dec. 10, with a 6-0 vote. Mayor Dennis Smith was excused.

The tribal council unanimously approved the agreement Nov. 20, Allen said.

“We negotiated a package that far exceeds what we currently are producing, but it allows for growth in Blyn’s future,” Allen said.

Currently Blyn operates on septic and individual systems, which Allen said are close to maximizing capacity.

“The casino is on a traditional wastewater system and we’re very desperate to upgrades its capacity,” he said.

Agreement

As part of the agreement, the tribe will pay the city about $1.59 million for a buy-in cost based on the percentage of piping and sewer capacity used at an initial 94,786 gallons per day, or 5.68 percent of the Water Reclamation Facility’s capacity.

City Attorney Kristina Nelson-Gross said even though the tribe is not required to pay state or local taxes or fees, it agreed to pay an equal amount for the project as an incentive for the city to approve the agreement.

She added that there won’t be any additional connections to the system from this line unless it’s from land owned in a state trust or in a reservation.

Along with the tribe’s properties, Sequim Bay State Park also will be connected to the system.

Sequim Public Works Director David Garlington said a lift station will be constructed in Blyn and another at the park to send waste uphill to Whitefeather Way and meet the city’s piping.

The tribe does not intend to bring in city water or reclaimed water, Allen said.

The agreement says the tribe can re-evaluate its capacity in five-year intervals starting in 2024.

What the construction impact will be to travelers is unknown at this time, Allen said.

The wastewater system will be installed along the south side of Highway 101.

“There will be some challenges there, but it’s not clear how much,” Allen said. “Traffic patterns haven’t been set. Once the contract has been set, we will coordinate with [state Department of Transportation] on Highway 101.”

Construction will last 10 to 12 months on the sewer line, Allen said.

Future projects

Allen said he expects the line to finish about six months before the hotel. A contract hasn’t been signed for the resort developer, he said, but the tribe is looking at a firm in the Pacific Northwest.

The tribe initially planned to begin work on the hotel in 2008 but the economic downturn led tribal leaders to delay it.

Long-term plans include adding up to 200 more rooms, Allen said. Resort CEO Jerry Allen has said the tribe will make a determination about two years after finishing phase one to see their next steps.

Right now, Ron Allen said the tribe is keeping a watchful eye on construction costs due to tariffs in place on materials like steel.

Tribal leaders anticipate the Jamestown Public Safety and Justice Center behind the Longhouse to be complete by March.

The $2 million, 5,000-square-foot building will hold a tribal courtroom, classroom, conference room and pop-up emergency operations center, and host space for Jamestown law enforcement and a Clallam County sheriff’s deputy.

Ron Allen said the tribe is also converting new space for miscellaneous operations and a new, small community center.

For more information about the Jamestown S’Klallam Tribe, visit www.jamestowntribe.org.

For more information about the interlocal agreement, visit www.sequimwa.gov or call 360-683-4908.

________

Matthew Nash is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. Reach him at mnash@sequimgazette.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading