Matthew Nash/Olympic Peninsula News Group                                Hemlock Street between South Fourth and Fifth avenues might be one of the worst rated roadways in the city of Sequim.

Matthew Nash/Olympic Peninsula News Group Hemlock Street between South Fourth and Fifth avenues might be one of the worst rated roadways in the city of Sequim.

Sequim staff plan repairs for roads damaged by winter weather

By Matthew Nash

Olympic Peninsula News Group

SEQUIM — Recent winter weather made some Sequim streets worse for wear.

Hemlock Street between South Fourth and Fifth avenues might be one of the worst rated streets in the city, and now drivers finding potholes at both ends of the road makes it hard to maneuver.

Matt Klontz, Sequim city engineer, said the road was rated about a 25 before the winter on the Pavement Condition Index, a study by consultants rating the pavement from 0-100 on how long it’ll last, but now it’s likely in the teens.

Two roads north, Prairie Street is in a similar condition, but city staff know the older roads in town are in bad shape.

David Garlington, Sequim public works director, told Sequim city councilors earlier this month that several streets in that area of the city are older roads where staff peeled sod off a field and put down asphalt.

“It’s almost amazing they’ve lasted as long as they did,” he said.

Throughout the year, city staff fill potholes and seal road cracks, but the cold mix and/or gravel they are laying down won’t last long, Garlington said.

City staff are considering purchasing a hot asphalt machine as one solution, and Klontz said they anticipate having a full inventory of winter damage to city streets in the weeks ahead.

Once compiled, he said they’ll put together a list for a contractor to perform repairs that might include full-depth dig outs in drier conditions, tentatively set for this summer. For now, city staff will continue to place cold-mix patches, Klontz said.

City rating

City staff do put bad roadways on their watch list when called, Klontz said.

They’ve used the Pavement Condition Index for about five years now as a way to rank projects to keep the overall streets at a higher rating, too.

Right now, the city is rated at 69, Garlington said.

“[A] 69 may sound bad, but I don’t think it really is all that bad,” he said.

“The aggregate of our city streets is [ranked] between good and fair and that’s not too bad. Every year that goes by, those streets degrade except for the ones we do repairs or an overlay to.”

Garlington said it would cost about $1.5 million a year to maintain a 70 rating.

However, he said the Pavement Condition Index algorithm shows them it can cost about four times more to fix a poorly rated street compared to preserving four to five streets of better quality.

Those living on poorly rated streets should see some relief in coming years, Garlington said.

“We’ve made a lot of progress here,” he said. “In a few years, we’re going to have many of those really bad streets in a condition that we’re not going to spend a ton of money on a small stretch of street. We’ll see a short-term drop, but a long-term upgrade to the citywide PCI.”

Brown Road is one project this summer that city staff said will improve its rating from a 55.

Klontz said they’ll preserve the pavement with a thin overlay and improve sidewalks at an estimated cost of $400,000 to $500,000 from Washington Street to Fir Street. They identified it because it could fail sooner due to its high traffic load, he said.

Road repair

While the priority projects are known, city staff said manpower and funding remain the key issues for repairing roads.

Garlington said the city continues to stretch dollars with chip sealing roads rather than paving, and city staff also seek out more economical and viable road materials.

They also are considering reducing street pavement widths because some are paved more than needed, he said.

Garlington said they’ve bumped up efforts for grants in recent years, an effort that has seen some success. By the end of 2016, the city accumulated about $3.6 million in transportation grants that can be used in the coming years.

However, Garlington said city staff have been working to increase the number of transportation projects while doing more design work in-house rather than paying consultants, but it’s led to slower delivery.

To help, Sequim city councilors approved in the city’s 2017 budget up to $68,000 for a temporary project engineer.

Annually, transportation revenue mostly comes from the city’s general fund at 5 percent to 7 percent of its total, Garlington said, accompanied by other sources such as the real estate excise tax, impact fees, sewer and water fees, and grants.

The Transportation Benefit District, approved in 2009, continues through April 2020 with a 0.2 percent retail sales tax within the city limits for safety, mobility, connectivity and accessibility transportation projects.

It generated about $643,000 in 2016.

Some of the city’s transportation projects in recent years include pavement preservation/rehabilitation, creating new sidewalks and repairing pavement.

Construction for one of Sequim’s worst sections, on Fir Street from Sequim Avenue to Fifth Avenue, tentatively will begin the end of this year or early next year.

For more information on the city of Sequim’s roads, call 360-683-4139 or visit www.sequimwa.gov.

________

Matthew Nash is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. Reach him at mnash@sequimgazette.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading