A new parking lot next to the Sequim Civic Center will be completed by the end of the summer, according to Sequim city staff. The city purchased three lots adjacent to the center in June 2022 to convert the properties into a parking lot. The lots also were known for common calls to 911. (Matthew Nash/Olympic Peninsula News Group)

A new parking lot next to the Sequim Civic Center will be completed by the end of the summer, according to Sequim city staff. The city purchased three lots adjacent to the center in June 2022 to convert the properties into a parking lot. The lots also were known for common calls to 911. (Matthew Nash/Olympic Peninsula News Group)

Sequim sets its list of projects

Summer work includes paving streets

SEQUIM — A number of infrastructure and road projects are on tap for the rest of the year in the city of Sequim.

Work to replace 61 deficient Americans with Disabilities Act (ADA) ramps across the city is anticipated to begin today by Earthwork Solutions, LLC.

City council members agreed on May 27 to an approximate $808,000 contract with an $80,800 contingency for the project. Earthwork’s bid was just under the city staff’s estimate, and it’s funded at about 82.4 percent by a Transportation Improvement Board Grant. The remainder will come from the city’s Transportation Benefit District and Stormwater funds, according to city documents.

Nick Dostie, Sequim’s city engineer and deputy director of public works, said the project has a deadline of substantial completion by mid-November.

Meanwhile, portions of Washington Street, West Sequim Bay Road and River Road are expected to be repaved this summer while Priest Road is anticipated to be rebuilt in the western portion of the city.

For the Washington Street pavement rehabilitation project, Lakeside Industries will place about 1,040 tons of hot mix asphalt along Washington Street from Seventh Avenue to Ninth Avenue.

Lakeside was the lowest of two bidders at just less than $443,300, but about $20,000 more than city staff’s estimate.

The project is funded by a Surface Transportation Block Grant at about 86.5 percent, staff report.

Lakeside also will pave West Sequim Bay Road from Whitefeather Way to the eastern part of Sequim city limits with 320 tons of asphalt.

Lakeside’s bid at about $104,000 was about $25,000 less than city staff’s estimate, and funding largely comes from the city’s Transportation Benefit District.

Lakeside also won with a $1.15 million bid, about $62,000 more than city estimates, to place 2,950 tons of hot mix asphalt and replace the subgrade on Priest Road. City staff said about 86.5 percent of the project is funded by a Surface Transportation Block Grant.

Dostie said a timeline for Washington Street and Priest Road’s construction will be determined at meetings on Tuesday.

As for work on River Road, he said Department of Transportation staff are reviewing the project that will pave the road from the U.S. Highway 101 overpass to the nearby roundabout.

Civic Center

The city’s new parking lot on West Spruce Street started the first week of June.

Dostie said they will look to wrap up the project this summer.

Hoch Construction of Port Angeles, which is finishing the renovation and expansion of the Sequim Library this summer, won the approximate $619,000 contract to level the lots from 153-169 West Spruce Street and create a gated parking lot with 40 spots north of the city hall. It will include four pay-to-use electric vehicle charging spots.

Originally slated for 2024, funding for the project includes 2024 General Facility Charges and General Fund monies, and funds from this year’s Real Estate Excise Tax (REET), general fund, and water and sewer funds.

Sequim bought the lots in June 2022 for $457,500 from the city’s Rainy Day funds with the intent to turn the sites into a parking lot.

The city had been in negotiations off and on with former owner Ron Fairclough for more than a decade, he said.

Law enforcement reported often to the properties for an array of charges related to Fairclough’s renters, he said. His home at 153 W. Spruce St. burned down in June 2021, along with a dental lab, garage and a fifth-wheel trailer.

Pedestrian bridges

City staff report that two pedestrian bridges budgeted and ordered in 2024 for Carrie Blake Community Park are anticipated to be shipped the week of July 21.

Dostie said if there are no damages in transit, they’ll seek a bid to remove the old bridge and install the new ones.

City council members agreed in the city’s 2024 budget for $350,000 to replace four aging pedestrian bridges across Bell Creek.

Public Works Director Paul Bucich said they are now only replacing one bridge on the Olympic Discovery Trail and adding one wide enough for a mower. Cost to manufacture the bridges was about $180,000, Bucich said.

Dostie said they hope to install the bridges sometime this year depending on when permitting comes through the state Department of Fish and Wildlife.

Other projects

City staff noted a few other upcoming summer projects:

• Paving the gravel path around the James Center for the Performing Arts’ bandshell in Carrie Blake Community Park.

• Stormwater improvements at the intersection of Brown Road and Washington Street will begin July 21 and finish in mid-August.

• Staff will inspect city parks and facilities for ADA-compliance for a Transition Plan.

For more about the city of Sequim, visit sequimwa.gov.

________

Matthew Nash is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. He can be reached by email at matthew.nash@sequimgazette.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading