Sediment, debris clog equipment at Elwha treatment plant

Silt-laden water is flushed into a side channel near the water intake for the industrial water treatment plant at the Elwha River west of Port Angeles Keith Thorpe/Peninsula Daily News

Silt-laden water is flushed into a side channel near the water intake for the industrial water treatment plant at the Elwha River west of Port Angeles Keith Thorpe/Peninsula Daily News

PORT ANGELES — Heavy loads of sediment and woody debris in a rain-swollen Elwha River are clogging filters and pumps at the Elwha Water Treatment Plant west of Port Angeles, Olympic National Park officials confirmed.

“Basically, they’re having to clean the filters a lot more frequently than anticipated,” park spokeswoman Barb Maynes said.

Drinking water is not being affected by the debris.

Port Angeles’ municipal water supply comes from a well near the river, not from the industrial water treatment plant that takes water straight from the river, Maynes said.

Water treated at the Elwha Water Treatment Plant, located 2.8 miles from the river mouth, goes to the Lower Elwha Klallam tribal fish hatchery, the state Department of Fish and Wildlife fish-rearing channel and the Nippon Paper Industries USA Inc. mill in Port Angeles.

Water leaving the treatment plant is well within standards, thanks to the efforts of crews, Maynes said.

“They’ve just been struggling keeping it maintained and on track,” Maynes said.

The Elwha Water Treatment Plant is operated by Veolia Water North America, one of several contractors involved in the National Park Service’s $325 million Elwha River restoration project that is keynoted by the removal of two dams.

A team of eight to 10 Park Service consultants and engineers was on site Monday and Tuesday making design modifications to the plant’s intake system.

“They’re trying to resolve it to get a permanent solution in place,” Maynes said.

The water treatment plant was designed to maintain fish-sustaining turbidity during removal of the Elwha and Glines Canyon dams.

Scientists have long known that removing the dams would trigger a large release of sediment that was stuck behind the dams in former lakes Aldwell and Mills for the better part of a century.

The anticipated sediment was the reason the treatment plant, fish hatchery and rearing channel were built in the first place.

“At this point, what I can tell you is that there have been some issues with the level of sediment and also organics — things like wood — working its way down the river,” Maynes said.

This debris caused a brief shutdown at the plant Sunday night. Workers have since been cleaning and monitoring filters, pumps and other equipment.

“It’s taking a lot more staff time and staff attention — and cleaning — to keep it operating,” Maynes said.

As of Tuesday, Maynes said there “haven’t been any problems” with the industrial water.

Nippon Paper Industries mill manager Harold Norlund was not immediately available for comment.

Maynes said the problem began “within the last week or so,” which coincides with a spike in river flows.

As river flows have ramped up, so have sediment and woody debris dislodged from the forest floor and reservoir beds.

Estimated river flows have soared from about 2,000 cubic feet per second last week to about 7,000 cfs over the weekend. The U.S. Geological Survey’s estimate for Tuesday afternoon was about 5,000 cfs.

Most of Glines Canyon Dam has been removed, allowing millions of cubic yards of silt, sand, cobble and gravel to flow over the top of what’s left of the former concrete high dam.

Elwha Dam was completely gone by March.

Dam-removal contractor Barnard Construction broke ground in September 2011 and expects to be finished with Glines Canyon Dam in May.

Maynes said it’s too soon to tell how fish are responding to the heavy sediment.

“Of course, it’s difficult to see them because the water is so muddy,” she said.

“There haven’t been very many collected at the hatchery. Lower numbers than last year are coming in, but that doesn’t mean they’re not out there.”

Reporter Rob Ollikainen can be reached at 360-452-2345, ext. 5072, or at rollikainen@peninsuladailynews.com.

More in News

Construction is in the early stages at the new Hurricane Ridge Middle School in Port Angeles. A special cement delivery vehicle brings another batch for the school’s foundation. (Dave Logan/for Peninsula Daily News)
Cement delivery

Construction is in the early stages at the new Hurricane Ridge Middle… Continue reading

Port Angeles approves donated building plans

Senior center reviews policies, procedures

Former legislator says state needs to better manage its forest land

Jim Buck tells business leaders an alternative is fewer public services

Clallam Transit eyes more linear bus routes

Plan would shift from loop-based service

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

The aurora borealis shines over Port Townsend late Monday night. Ideal conditions to view the event are from about 9 p.m. to 3 a.m. with clear skies and away from city lights or higher locations with northern views. (Steve Mullensky/for Peninsula Daily News)
Northern lights

The aurora borealis shines over Port Townsend late Monday night. Ideal conditions… Continue reading

Jefferson County board sets annual goals

Discussions include housing, pool, artificial intelligence

Clallam commissioners to continue policy discussions on RVs, ADUs

Board decides to hold future workshop before finalizing ordinance

Port Angeles School District community conversation set Thursday

Individuals who want to talk to Port Angeles School… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii