OLYMPIC NATIONAL PARK — After removing 850 truckloads of dirt, workers were still toiling Tuesday to get to the bottom of the fill washed out when about 100 feet of Hurricane Ridge Road collapsed — eliminating the only paved road to the top of the mountain.

The work to remove the fine-grained fill that was used to build the road when it opened in 1958 is slightly behind schedule, said Olympic National Park spokeswoman Barb Maynes.

Original estimates were that the fill removal would be finished Monday or Tuesday, but revised estimates put completion at the end of today, Maynes said.

She said the delay shouldn’t affect the overall estimate to reopen the road in early March, six weeks after its Jan. 18 slipout.

The job is contracted at $1.4 million. Federal Highway Administration engineers estimate that the total cost will exceed $2 million when the work is done.

The two-lane road to the popular snow recreation area, Hurricane Ridge, 17 miles south of Port Angeles, crumbled about a half-mile north of Heart O’ the Hills campground, blocking all highway access past the slipout.

No detour was possible around the washout, park officials have said.

“They [Bruch & Bruch Construction Inc. of Port Angeles, which was hired for the job,] have now removed about 17,000 cubic yards of fill,” Maynes said.

“That translates, roughly, to about 850 truckloads.”

As the workers dug deeper down the 65-foot cliff of fill, the sediment was more and more saturated with water.

“With more water in it, they can’t put as much in the truck,” Maynes said. “So that slowed them down just a little bit.”

After reaching the bottom of the embankment, the crews will replace a 24-inch culvert, through which water passes under the road, with a 42-inch culvert.

“That way, it will allow more water to pass through more efficiently,” Maynes said.

She said that it doesn’t appear that the present culvert failed.

“As they continue digging, and it is wetter and wetter, there is some indication that there was some leakage, but there wasn’t a massive failure,” she said.

Maynes said workers also will install what are called rock drains — or French drains — that will help water to pass through in other areas besides what goes through the culvert.

“They’ll also bring in some rocks to rebuild some of the slope to help with drainage in other areas.”

Instead of the fine-grained fill, the road will be rebuilt using heavier rocks and rougher grain sediment, Maynes said.

“That was built many years ago, and it is not the standard we will use today,” she said. “This will help prevent it from happening again.”

Other portions of the road built upon fill could see the same fate if they become too saturated, park staff have said.

__________

Reporter Paige Dickerson can be reached at 360-417-3535 or at paige. dickerson@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading