Roadwork to create more jams on Sims, in downtown Port Townsend

PORT TOWNSEND — Local traffic will get a lot worse before it gets better, as separate road projects are in progress at either end of town.

Construction of the second roundabout at Thomas Street and Sims Way — state Highway 20 — began last week, with detours scheduled to begin today.

At the same time, the start of the downtown streetscape project has been postponed one week, until May 1.

Both projects will cause traffic slowdowns, forcing both local residents and tourists to allow extra time to reach their destinations.

The roundabout construction is a shorter-term project, scheduled for completion prior to the heaviest tourist season.

But the streetscape project, because of its scope and location, has a larger impact on a greater number of people for a longer time.

The multiphased streetscape project is located in a historical district that also serves as a commerce center, forcing the city to accommodate different needs.

For instance, the repaving of Madison Street will be done in stages to provide constant access to the businesses in proximity to the construction.

And in September, which is prime festival season, the construction will take a hiatus.

“Because of the film festival and other events, we will shut down in September,” said project manager Tom Miller.

“We will establish safe routes around what we have done at that time, so people can have access.”

By then, the waterfront park could be completed with a sculpture, Gerard Tsutakawa’s “Salish Sea Circle,” already in place.

With all the delays and the accommodation of scheduled events, Miller can’t say when parts of the project will be done, but he hopes the entire streetscape effort will be completed by Jan. 1.

Miller has established what he believes to be a realistic schedule, but he admits “there are always things that you don’t anticipate making things take longer than expected.”

If building the streetscape resembles a careful walk downtown, the roundabout more resembles a sprint.

Beginning today, inbound traffic will be rerouted along Fourth Street while outbound cars will use one lane on Sims Way.

How traffic routes will change the pattern cannot be predicted, according to Bruce Seton Jr., who is running the project.

Development Review Engineer Samantha Trone expects the roundabout to be completed by the end of May.

Following this, the median strips, landscaping and final paving will occur.

________

Jefferson County Reporter Charlie Bermant can be reached at 360-385-2335 or at charlie.bermant@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading