Rayonier mill site cleanup pushed back another year

Rayonier mill site cleanup pushed back another year

PORT ANGELES — The time line for the Rayonier cleanup has been pushed back by another year.

The state Department of Ecology is now requiring Rayonier Inc. to have a cleanup plan for its former mill site finished in December 2014 rather than the end of 2013.

The cause is both the long-delayed release of Ecology’s Port Angeles Harbor pollution study and a two-month extension of its public comment period, said Rebecca Lawson, regional manager for Ecology’s toxics cleanup program.

The $1.5 million study, released last month, was initially expected to be finished in 2009, a year after samples were taken.

That was delayed due to disagreements with Ecology’s contractor over the extent of the study, Lawson said.

Ecology has long been criticized for the slow-moving Rayonier cleanup effort.

“I know some people think this just keeps going on forever,” Lawson acknowledged.

“This [the harbor study] is a significant body of work.”

The delay of that study affects Rayonier’s time line because it must use the study’s findings to come up with a plan for cleaning up 1,325 acres of harbor sediment near its former mill.

“Their time line doesn’t start ticking until we get the report,” Lawson said.

She estimated that the harbor study should become final in July.

That’s about four to five months later than listed in Ecology’s agreed order with Rayonier, signed in 2010.

The delay wasn’t entirely unexpected.

Lawson estimated when the harbor study was released that the time line would be pushed back by about six months.

Last week, Ecology also decided to extend the study’s comment period from 30 to 90 days, causing further delay.

The extension was done at the request of the city of Port Angeles, Port of Port Angeles and Olympic Environmental Council who wanted more time to review the extensive document.

“I think that’s necessary because people need time” to review it, Lawson said.

“It does no good if we rush our way through.”

The 75-acre property, the largest undeveloped waterfront parcel on the North Olympic Peninsula, became an Ecology cleanup site in 2000 due to concentrations of petroleum, metals, polychlorinated biphenyls, dioxins and pesticides.

The mill closed in 1997.

Lawson attributed past delays to disagreements between Rayonier and Ecology over the extent of the cleanup site, settled in the meantime with the signing of the agreed order, and the project previously being handled by the agency’s solid waste division, rather than toxics cleanup.

Toxics cleanup took it over in November 2007.

When asked about the project’s delays, Lawson emphasized the positive.

“We’re more on the same page now,” she said, referring to Ecology and Rayonier.

“A lot is happening, and we are working very productively on Rayonier.”

Lawson said the harbor study is the biggest report done to date as part of the cleanup effort.

She didn’t discount the possibility of additional delays but said they likely would not be as extensive.

“We want to get through this as quickly as possible,” Lawson said.

“It’s not just about how quickly we can do it,” she added.

“We do need to do it well.”

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading