Mark Johnson

Mark Johnson

Railroad Bridge trestle replacement crews taking special measures to spare wildlife

SEQUIM — A $1.53 million project to construct a 750-foot-trestle over the Dungeness River requires crews to navigate thick woodlands and cross the waterway without disturbing wildlife, said the president of the construction company performing the work.

Crews with Nordland Construction NW of Port Townsend began removing a damaged trestle from the west side of Railroad Bridge on Monday in preparation for replacing it and reopening the link on the Olympic Discovery Trail.

About 30 percent of the present 570-foot-long wooden trestle had been removed as of Wednesday, said Thomas Johnson, president of Nordland Construction, which is using design and engineering schematics by Otak of Portland, Ore.

The trestle will replace the existing one on the bridge in Railroad Bridge Park, 2151 W. Hendrickson Road, which was damaged by the rain-swollen Dungeness River during a Feb. 6 storm.

The bridge itself is undamaged, but traffic over it has been closed since February because the trestle connecting it to the west bank is unsafe. That blocked use of a portion of the 140-mile Olympic Discovery Trail, which will eventually span the North Olympic Peninsula from Port Townsend to LaPush.

The Jamestown S’Klallam tribe owns both the park and the bridge, and recently received the permits required to begin construction on a replacement.

The bridge is expected to be reopened after work is completed in December.

Crews are taking special measures to do the work without disturbing salmon and other wildlife.

“We are going to make another 800-foot access road to the side of the perimeter alignment,” Johnson said, noting that the current pathway on the west side of the river is not large enough to accommodate large machinery.

The temporary roadway will include an 89-foot-long railroad car bridge that will span the river channel, allowing machinery to move across and onto an island in the center without entering the waterway.

“We have to be extremely careful about disturbing any spawning salmon,” said Pat McCullough, owner of ESA Inc. of Belfair and subconsultant to Otak.

The temporary bridge will be set using a small crane, he said.

Once the new roadway is in place and the old trestle has been completely removed, crews will begin driving steel pilings that will support the new trestle into the ground at four locations.

Concrete piers will be placed on top of the pilings to hold up the trestle.

The piers will be about 50 feet long and consist of 16.5-inch walls, McCullough said.

A concrete pier beneath the existing Howe Truss bridge will support the new trestle where the two structures connect.

The final phase will be to lower a walkway onto the piers with two massive cranes, McCullough said.

“I imagine it will be at least two 200-ton cranes — one on each side” of the river channel, he said.

The new trestle will arrive in prefabricated 60-foot-long, 9-foot-deep sections, and crews “will bolt them together,” McCullough said.

The new trestle will be longer than the existing one and includes four 182-foot-long sections with one 22-foot-long section in the middle.

The old trestle previously was propped up in 38 areas by five creosote poles in each location. The depth of the pilings varies from 6 feet to 25 feet.

All 33 remaining creosote supports from the river bed will be removed. Five were removed previously in early August.

The replacement trestle will allow logs and migrating salmon to pass beneath without hindrance by reducing the number of support beams needed to prop up the walkway to four.

________

Sequim-Dungeness Valley Editor Chris McDaniel can be reached at 360-681-2390, ext. 5052, or cmcdaniel@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading