Pricetag for Port Angeles waterfront plan soars

PORT ANGELES — City Hall will have to spend an additional $700,000 to finish a portion of its Waterfront and Transportation Improvement Plan, after a contract came in at more than $1.2 million.

The total cost of creating the plan is now at about $1.7 million.

Following staff direction, the Port Angeles City Council on Tuesday night unanimously approved spending the additional funds to pay for the construction drawings needed to implement about half of the waterfront redevelopment aspect of the project.

The drawings, which include engineering and planning documents, are the main part of the second contract for the project with Studio Cascade of Spokane.

That contract came in at nearly $1.253 million, over four times higher than initially anticipated in August, and $700,000 over what the city had budgeted for the project this year.

The first contract with Studio Cascade, which involved about a half-dozen subconsultants, cost $484,000.

It included designing the waterfront improvements, new entryway and directional signs, and starting a citywide transportation plan.

When the city began working on it more than six months ago, the plan was anticipated to cost around $778,000 to develop.

The additional money would likely come from the city’s economic development fund, said Nathan West, city economic and community development director.

Several council members, noting the need to improve the waterfront and community support for the project, voiced support for spending the additional money.

“The community is behind this project,” said Mayor Dan Di Guilio.

“I think we as a council have a responsibility to do what we can to make this happen.”

Council member Brad Collins questioned whether the economic development fund should be used. He said the fund should be used to create jobs.

Other council members disagreed.

“It will create jobs; it will revitalize downtown,” said Deputy Mayor Don Perry.

West said the price tag increased so dramatically because the scope of the waterfront plan changed during the public input process.

Initially, it was mainly going to be limited to the west end of downtown, West said, but was expanded in response to comments from the public to include other areas, such as City Pier and Hollywood Beach. A west end beach was also added to the design.

“They [public] have a lot of interest in getting a variety of improvements on the waterfront that perhaps weren’t anticipated,” West said, adding, “we’re happy with the direction that we’re moving in.”

The waterfront plan is estimated to cost $17.3 million to fully implement.

Acknowledging that the plan is too much for the city to chew, at least in one sitting, the council also Tuesday directed Studio Cascade and its subconsultants to draft only construction drawings, including engineering and permitting documents, for the west half of the waterfront project.

That move reduced the cost of the second contract by about $1.1 million.

The west half includes a boardwalk west of the ferry terminals, new park on the east side of the Valley Creek estuary, and landscaping and road improvements along the west half of Railroad Avenue. All together, those improvements are estimated to cost $7 million.

What’s left out: improvements to City Pier, Laurel Street and the other half of Railroad Avenue, and expansion of Hollywood Beach.

West said he still hopes to begin work on the waterfront sometime this year.

But he acknowledged before the meeting that grant funding has dried up in the last few years, and the city may have to throw up some cash to get it started.

West said his staff has not had the time yet to pursue any grants, but added, “I’m not ready to rule it [grant funding] out as an option.”

City Manager Kent Myers told the council that the city is seeking funding through the U.S. Economic Development Administration.

West said Victoria Express, which wants to move to what would be a new waterfront park, may also help with the new improvements.

The city has estimated that city funds will make up 20 percent of the waterfront project’s cost.

The first six of the 62 new directional signs planned as part of the plan will be installed next month. The rest will be installed throughout the year.

The design of two new entryway monuments, controversial because one would be located at the bottom of the Morse Creek S-curve, remain on hold.

The transportation plan will be done by 2013, said Roberta Korcz, city assistant planner.

For more information on the waterfront project, visit www.pa-waterfront.org/intro.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading