Port Townsend roundabout set to open to traffic

PORT TOWNSEND — The roundabout on the corner of Thomas Street and Sims Way is slated to open to unobstructed traffic in time for Memorial Day, but drivers may experience delays until then.

The project will be completed sooner than expected, city officials said.

“There will be a lot of one-lane traffic situations over the next week,” said City Engineer Dave Peterson.

“There will be many delays, but it will be open by the weekend.”

Construction on the roundabout, the second to be constructed this year, began April 19. It is part of a $7.1 million project that also will add landscaping, medians and sidewalks.

The Thomas Street roundabout was scheduled to open in mid-June, but the contractor “worked hard in order to finish sooner,” Peterson said.

During construction, traffic will alternate between single lanes or drivers will be encouraged to use detours.

When there is no construction under way, traffic from each direction will be able to travel through — but not completely around — the roundabout.

“They’ve done a good job keeping traffic moving,” Peterson said of Seton Construction, which built both the Taylor Street and the Howard Street roundabouts on Sims Way.

The Howard Street roundabout was finished in April.

Other work through June

Landscaping and the construction of traffic islands on the Taylor Street roundabout will continue during June, with final paving scheduled for later in the month.

As a final step, the surfaces will get another 4 inches of asphalt, which will bring the road to the same height as the bottom of the curb.

During the final paving, traffic again will be reduced to one lane, Peterson said.

Besides the roundabouts, landscaped medians are planned from Howard to Thomas streets.

New sidewalks on both sides of the street and pedestrian crossings will improve the area for those on foot, city officials said, while bike lanes will be added, along with connections to the trail networks, to the north and south.

Storm water will be treated and detained with ecology embankments and two storm-water detention and treatment ponds.

Lawsuit

No date has been set to hear a lawsuit against the city for the roundabout that was filed March 24 in Jefferson County Superior Court by Vintage Hardware co-owner Ken Kelly.

Kelly, who said the roundabout was illegally installed and is harming his business, is suing for unspecified damages.

“Since this began we haven’t had any vacation visitors, buses or campers stopping at the store,” he said. “It has drastically cut our income.

“It is a business killer,” he said.

The Kellys ask the court to set the amount of damages for an expected loss of business and devaluation of property once the roundabout is constructed.

Kelly is not impressed with the speed of the roundabout’s construction or its craftsmanship, calling it “shoddy.”

Contractors plan to spend much of June filling in cracks and applying finish work.

Any hearing on the suit will occur well after the roundabout is in operation.

This doesn’t cool Kelly’s ardor.

“Anything that is done can be undone,” he said.

Kelly said that construction will place a wall across the front of his business, blocking direct access from Thomas Street, and eliminate parking spaces while making it hard for impulse travelers to stop.

The roundabout will block the access to a portion of Fifth Street, which allowed large vehicles to pull up parallel to the curb in front of his store, Kelly said.

City Attorney John Watts said that Kelly developed this street on his own and did so on city property.

Watts said the city has acted properly during the construction and has not infringed on Kelly’s property.

“We are changing the use of a city-owned right of way, which we always had the right to do,” Watts sad.

“As this is city property, we have the right to relocate improvements.”

________

Jefferson County Reporter Charlie Bermant can be reached at 360-385-2335 or at charlie.bermant@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading