Port Townsend council approves funding to repave city’s Tyler Street

Contractors expect project to be done in 30 to 40 days

PORT TOWNSEND — The Port Townsend City Council approved an additional $178,000 needed to meet the lowest bid for work planned on Tyler Street.

The project in total was listed at $732,000 in the council’s agenda packet Monday night. The lowest bid for the portion of the project currently underway came in at $463,635.

“I still think this is an amazing project,” Public Works Director Steve King said. “It’s fixing a huge liability and that road has just tanked in the last few years. Overall, huge value. But it is a significant cost increase, I want to point that out.”

The work could start soon, King said.

“We met Friday with Northern Asphalt, the apparent low-bidder, and their sub-consultant Sound Concrete,” King said. “They have an opening in their schedule and they want to get contracts signed, like immediately, and be out there in like two weeks to try to knock it out.”

The contractors have an aggressive schedule and hope to complete the project in 30 to 40 days, King said.

The work will include paving over the street from Lawrence Street to Jefferson Street and adding a cement-treated base.

“It’s just like an old house,” King said. “When you start uncovering it, you find out how bad things are. We’ve added cement-treated base, like we did on the test strip on Lawrence, so we can pave Tyler Street and hopefully not come back to it for 20 years.”

King said previous patch jobs done near the Port Townsend post office in 2019, which lack cement-treated base, already are failing.

The city also will complete an ADA-accessible route on the sidewalks between Lawrence Street and Jefferson Street, King said.

Northern Asphalt was the lowest of six bids that came back recently, King said.

Originally out to bid in 2024, the Tyler Street repave was planned to be completed in conjunction with work being done on Lawrence Street.

After receiving no bids, with contractors overbooked, the city put Lawrence Street out to bid alone, King said. That work has now been completed, he added.

King presented the council with three choices. Accept the lowest bid, reject the lowest bid to re-bid, or reject the lowest bid and abandon the project. King said staff recommended the first option.

He said he doubted going to re-bid would generate lower bids.

The bid process itself would add $30,000 to $50,000, a typical sum, and the project would be pushed until probably September, a busy season for the Port Townsend Farmers Market, located at 650 Tyler St.

“There’s now potholes and trip hazards where the farmers market resides, so we can’t have that,” King said.

King said the work, which likely will overlap with the opening weeks of the farmers market, is unlikely to interrupt the market.

There will be a several day period of actually paving of the street, but most of the work will take place on the sidewalks, he said.

Abandoning the project would mean losing grant money and letting the road fail, King said.

The $178,000 approved Monday will come from Transportation Benefit District (TBD) dollars, King said. That is in addition to the $145,000 already budgeted from the TBD, he added.

The city received a $379,354 pavement preservation grant from the Transportation Improvement Board in 2022. The grant does not cover sub-grade cement treatment, King said.

King said the way the bids have gone, the city only qualifies for $305,840 of the funding. King added that he has requested that the state let the city keep the remainder to reduce the cost to the TBD, but he does not expect it will.

“That grant was intended to overlay the street only,” King said. “That grant also intended that our staff would do some small patching dig-out pavement repair, where the pavement was starting to fail.”

King said he’s grateful that voters supported the formation of the transportation benefit district and that he expects other projects to use the fund significantly.

“It’s not getting any better. We are 10 years late to the game on some of these streets,” King said. “I look at them every day. You just get a little bit of rain and let the pavement dry, and you can see all the cracks.

“In the five years that I’ve driven all these streets, it’s just got significantly worse.”

________

Reporter Elijah Sussman can be reached by email at elijah.sussman@sequimgazette.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading