The Port of Port Townsend boat yard is operating below capacity, one participant said at a public meeting with port commissioners and staff members. (Jeannie McMacken/for Peninsula Daily News)

The Port of Port Townsend boat yard is operating below capacity, one participant said at a public meeting with port commissioners and staff members. (Jeannie McMacken/for Peninsula Daily News)

Port of Port Townsend sets start date for south jetty rebuild

PORT TOWNSEND — Port of Port Townsend commissioners have set a mid-September start date for demolishing and replacing the failing Point Hudson south jetty.

The vote taken late in the evening Wednesday night reversed an earlier unanimous vote to request bids for two start dates: July 1 and mid-September.

The call for bids should go out within two weeks, staff members said, because construction companies are bidding on projects for the year now. No date was set to issue a call for bids.

Commissioners also authorized staff to submit a request the City of Port Townsend to rezone Point Hudson to allow for expansion of recreational vehicles at the northwest corner of the property.

The three-hour business meeting saw spirited debate between commissioners and staff and the public, many of whom are port tenants.

During the public comment session, speakers continued an ongoing debate regarding the port’s financial health and offered to help staff develop a fiscal oversight system.

At the beginning of the session, Commissioner Pete Hanke set the tone for the evening by asking everyone gathered to respect one another.

“We’re all on the same team and we’re all working together for the same goal,” he said. “No derogatory comments. We value your opinion and it’s really important that we’re not trying to knock the staff or the commission down.”

The south jetty project is estimated to cost $3,067,000. The port has received a $1,059,173 grant from the Washington State Recreation and Conservation Office. Last fall, commissioners directed staff to move forward on the process of issuing a $3.2 million limited tax general obligation municipal bond to cover the rest of the project costs.

Director of Finance Abigail Berg had recommended a $3.2 million bond because it would be easier to lower the bond amount during the bonding process rather than raise it later if the project runs over its projected budget.

A limited tax general obligation bond is a type of municipal bond that is guaranteed by the agency’s pledge to use all legal resources, including the levying of property taxes up to a set statutory limit.

On Wednesday night, discussion centered around the economic cost to the port and to the city, depending on when the project would begin.

If the project began in July, it would impact the city’s tourism season, it was decided. A mid-September date was seen as preferable because it would avoid the summer months and also would be after the popular Wooden Boat Festival, set this year for Sept. 7-9.

While commissioners deliberated, port Executive Director Sam Gibbony told them, “We can go out to bid with unknown results. They can come back much higher than expected.

“The way to achieve the best possible result is to have the entire window open,” she said. “This will increase your chances of getting the lowest responsive bidder.”

After a lengthy review of the possible closures that would restrict the number of days and hours that work can be done, Hanke made a motion to amend the bid process to include only the September start date. It passed by two votes with Commissioner Stephen Tucker abstaining. He did not explain why he was abstaining.

The two Point Hudson breakwaters are failing and in need of replacement.

Replacement of the north breakwater at Point Hudson is estimated to cost $2,253,000. That project will not start until 2019.

Point Hudson serves as the hub of the Northwest Maritime Center’s biggest annual events, such as the Wooden Boat Festival and Race to Alaska.

The jetties are among more than $9 million in port capital projects scheduled until 2020.

More RV sites

Commissioners and staff also discussed expanding the number of RV sites at Point Hudson as a way to increase revenue.

Point Hudson now has 48 spots at the Waterfront RV Park. The 15 new sites would be away from the water in a empty lot at the northwest corner.

Director of Planning Eric Toews said his “ back-of-the-envelope rough calculations “ for 15 sites would equal $100,000 per year in revenue.

Many members of the public questioned his numbers.

“The cost of doing this will not be trivial,” resident Ernie Baird said. “You will use considerable staff time and where are the construction costs?

“You are gambling, you are walking into a buzz saw. Point Hudson has a great emotional value for many people in the community. It’s a gamble and not a wise one.”

Chris Bakken, Sea Marine manager commented, “My calculations say the revenues are $40,000, not 100k, per year. It is not cheap to store RVs. A lot of improvements have to be done on this property.”

Jake Beattie, executive director of the Northwest Maritime Center, questioned this action.

“I was both surprised and a little bit disheartened that this is here,” Beatte said. “There’s a lot of surprise in the room. I agree that you guys are going to need every conceivable avenues of revenue enhancement. I also think you are going to need friends and this is not going to make friends.”

Peter Langley, owner of the Port Townsend Foundry, also spoke against the idea.

“I’d like to see Point Hudson encourage more marine trades, less RVs,” he said. ”I know we are strapped for money, but as a taxpayer I’d pay more money to keep Point Hudson in marine trades and manufacturing. Let’s keep our waterfront working.”

Commercial fisherwoman Pam Petranek asked, “Why is our work yard empty? We must be competitive.

She claimed that port yard rates are almost twice that of surrounding yards.

”Lower the rates to fill the yard,” she said. “Boats support businesses, the port and Jefferson County. Our yard is empty compared to years past. It should be filling up right now.”

After the meeting, Beatte said he felt that community interest is growing.

“I think the silver lining is that the greater community is starting to realize the importance of the port and marine trades,” he said.

”There is a lot of dialogue right now. I’m an optimist. I have faith that it will lead to us being stronger as a community.”

________

Jeannie McMacken is a freelance writer and photographer living in Port Townsend.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading