Port of Port Townsend continues to work on contract for dock work

PORT TOWNSEND — After the apparent low bidder dropped out, Port of Port Townsend leaders are now in final discussions with an Anacortes company that could lead to a contract award to replace the dilapidated Boat Haven marina AB Docks.

Culbertson Marine Construction’s bid of $3.46 million being the second lowest of nine bids submitted to the port a month ago.

Representatives of the company are in final discussions with port Executive Director Larry Crockett, who expects to bring back the paperwork for port commissioner approval and contract signing within the next two weeks.

“They have indicated they may be able to complete it ahead of schedule, by the end of this year, which is great,” said port Commissioner John Collins.

The original apparent lower bidder was Redside Construction LLC of Port Gamble at $3.08 million, but Crockett said the company pulled out of the running. Some miscalculations were made in its bid, he said.

Crockett has said he and port officials must ensure that the contractor would be both “responsive and responsible” to carry out the work.

The project will replace aging recreational boat docks and slips for about 100 boats.

All but one of the bids opened at the port offices were under the port’s engineering estimate of $3.96 million.

About 24 firms contacted the port in recent weeks about bidding on the project, but nine actually submitted bid packages.

Out-of-water work is expected to begin shortly after the contract is awarded, but actual removal of the old and installation of the new docks cannot take place until after the annual Wooden Boat Festival ends Sept. 12, when boats can be temporarily relocated to Point Hudson Marina while work is done at the Boat Haven.

In-water work would have to be completed by Feb. 15 when the state closes the allowable in-water work period intended to protect migrating salmon.

Electrical work and installation of gangways can still be done when the fish window closes to in-water work because it is above water and does not disturb salmon migration.

Financing has been secured for renovation of the AB Docks built in 1967, Crockett said, with the revenue bonds a lower prices because of the stock market decline.

The docks were given a life of 25 years when they were built, Crockett said, which meant they should have been replaced in the early 1990s.

The AB Docks project, like Point Hudson Marina’s upgrade in 2006-2007, would be upgraded to American with Disabilities Act specifications, city building codes, although space for about 13 boats would be lost.

________

Port Townsend-Jefferson County Editor Jeff Chew can be reached at 360-385-2335 or at jeff.chew@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

The aurora borealis shines over Port Townsend late Monday night. Ideal conditions to view the event are from about 9 p.m. to 3 a.m. with clear skies and away from city lights or higher locations with northern views. (Steve Mullensky/for Peninsula Daily News)
Northern lights

The aurora borealis shines over Port Townsend late Monday night. Ideal conditions… Continue reading

Jefferson County board sets annual goals

Discussions include housing, pool, artificial intelligence

Clallam commissioners to continue policy discussions on RVs, ADUs

Board decides to hold future workshop before finalizing ordinance

Port Angeles School District community conversation set Thursday

Individuals who want to talk to Port Angeles School… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading