Port of Port Townsend aims for 2022-23 finish

Breakwaters top priority in Point Hudson plan

PORT TOWNSEND — The Port of Port Townsend aims to finish replacement of the two Point Hudson jetties in 2022 or 2023 at a cost of $13.4 million.

Commissioners approved on Thursday several aspects of jetty work. The next steps are the redesign and permitting process.

Much of the early work, such as the permitting process, will be funded by the port’s Industrial Development District (IDD) funds. The physical work, when it comes time for that, will require outside funding.

“Moving into the work of the actual phases will be a heavy lift for the port and will require an all-hands-on-deck approach,” Executive Director Eron Berg said.

“To be clear, even with the IDD funding in place, the port will not be able to fund all of this work without outside dollars,” he said.

Two aging jetties protect the Point Hudson Marina. The repair and preservation of the more than 80-year-old jetties are the Port of Port Townsend’s top priorities when in a three-phase preservation plan. (Ken Park/Peninsula Daily News)

Two aging jetties protect the Point Hudson Marina. The repair and preservation of the more than 80-year-old jetties are the Port of Port Townsend’s top priorities when in a three-phase preservation plan. (Ken Park/Peninsula Daily News)

Berg will execute an amendment to the scope and budget of professional services agreement with Mott MacDonald Engineering Inc., which is putting together the project bidding documents. This agreement will cost $373,000.

Commissioners also approved a second personal services agreement, costing $36,000, with Artifacts Consulting Inc. Artifacts will prepare historic and cultural resource inventory and report as part of the preservation plan.

The best-case scenario has the project completed by late spring or early fall 2022. The worst-case scenario expects it to be finished by spring or fall 2023.

Port officials have discussed for years how to rehabilitate or replace the north and south jetties, which are over 80 years old and have slowly been falling apart due to age and damage from storms.

The work is part of a three-phase Point Hudson Preservation Plan.

“Replacing the overlapping jetties that protect the marina is the first and most critical phase of the preservation plan,” Berg said.

“Put simply, without these jetties we would no longer recognize Point Hudson,” he said.

“Many businesses would be shuttered and community activities like the Wooden Boat Festival would cease.”

Since 1934, the jetties have been rehabilitated twice. They underwent a major overhaul in 1969 and minor repairs in 1996. Many of the materials of the jetties now are at or well beyond their useful life, compromising the stability of the structures themselves, studies have found.

(Ken Park/Peninsula Daily News)

(Ken Park/Peninsula Daily News)

Port officials and key community stakeholders were presented with two options for rehabilitation: either encapsulate the existing structure, minus a few creosote timber piles to mitigate permitting issues — which would reduce demolition costs and maintain the current aesthetic — or demolish the whole thing and replace it with better materials but with the historical design options in mind.

The stakeholders — which include the City of Port Townsend, Jefferson County, Public Utility District, Jamestown S’Klallam Tribe, Northwest Maritime Center and the Washington Trust Historic Preservation — ultimately went with the total replacement option.

Replacement protects the Point Hudson Marina and its operations for the next 30 years from wind and vessel waves as well as the inevitable rise in sea level, said Shane Philips, president of Mott MacDonald Engineering Inc., in his presentation on Thursday.

It also maintains the aesthetics, while using environmentally acceptable and updated materials, he added.

________

Ken Park can be reached at kpark@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading