Port of Port Angeles to hold off on $3 million Terminal 1 project

PORT ANGELES — The Port of Port Angeles will delay the $1 million startup of a multiyear $3 million Terminal 1 pile-replacement project until 2015.

The project delay is among several 2014 capital-project delays and deferrals, port commissioners learned Tuesday.

In all, $1.4 million of the port’s $2.7 million 2014 capital budget has been deferred or delayed, Chris Hartman, port director of engineering, told commissioners as part of his second-quarter 2014 report, which covers January through June.

Schedule delays for the Terminal 1 and marine trades area cleanup off Marine Drive were based on permitting or coordination issues, Hartman said in a later email.

Deferred projects are being rescheduled to future years for such reasons as permitting agency staff turnover, complicated permitting requirements or other reasons, he said.

The $1 million in construction on Terminal 1 — where toxic, creosote-covered timber pilings will be replaced with stronger, environmentally safer steel piles — was slated to begin in October.

Now, it will begin in July 2015, Hartman said.

Construction must be completed by 2017, he said.

‘Still on track’

“We’re still on track there,” he told the commissioners.

The port already has spent $73,826 of $180,000 for redevelopment-permit costs and project design, Hartman said.

He said the Terminal 1 project holdup was due to permitting delays and, in part, turnover at the Army Corps of Engineers.

The permit also was a more comprehensive “full harbor programmatic permit” that outlined 10 years of anticipated improvements to other port’s piers rather than solely Terminal 1 improvements, he said.

“It looks at all our facilities and says, ‘In the next 10 years, we anticipate needing to do this many pile replacements at each of our facilities,’” Hartman said in an interview after Tuesday’s meeting.

Patricia Graesser, spokeswoman for the Corps of Engineers’ Seattle district, said Tuesday in an email that the permit covers maintenance activities at five terminals, including Terminal 1, and at log rafting areas and the Boat Haven marina.

The public comment period on the permit ended April 17.

“We are currently reviewing the project for compliance with the Endangered Species Act, tribal coordination and the National Historic Preservation Act,” she said.

The transit shed at Terminal 1, built in 1926 as the port’s first development, is eligible for the National Register of Historic Places and would be demolished, according to the public notice asking for comment on the project issued jointly by the Corps and the state Department of Ecology.

“It is not possible to predict a specific date for completion of the review and coordination process, as it involves entities outside the Army Corps of Engineers.

The improvements to Terminal 1, where 900-foot vessels dock for repairs and maintenance, will be funded in part with a $1.5 million U.S. Economic Development Agency grant that will not be endangered by the construction delay, Hartman said.

Terminal 1 was among two delayed and four deferred projects cited by Hartman in his presentation to the commissioners.

Marine trades area

A $250,000 cleanup project also will be delayed for the port’s marine trades area on Marine Drive near the site of the former Peninsula Plywood mill.

Funding was deferred for replacement of a security truck to allow for purchase of a more fuel-efficient vehicle in 2015.

Also deferred was an upgrade to the port’s virtual server, a fire-suppression upgrade for the port’s information technology room and acquisition of a gangway transition tower that would help cruise ship passengers disembark.

Port officials have borrowed a gangway system for this year’s cruises.

Projects completed include purchase of a $199,456 log loader.

The 23 projects still scheduled for 2014 include $160,000 in vehicle access improvements to William R. Fairchild International Airport, which is 75 percent complete and will be finished by mid-September, Hartman said.

They also include construction of a $100,000 stormwater treatment facility, which is 48 percent complete, he said.

“A number of projects are in planning stages or are moving toward construction now,” he said.

For eight of the projects still on schedule for 2014, nothing has been spent year-to-date, Hartman said.

Port security

In other action, port commissioners heard a report on a $701,063 federal grant to upgrade port security that was $67,336, or 9 percent, less than the $768,399 requested by the port for ID security, cybersecurity, camera and lighting improvements.

The port had applied for funding for 75 percent of the project cost of $1.02 million, with the port covering the remaining 25 percent, or $256,133.

The new project cost is $934,751.

The Federal Emergency Management Agency will decide by September “which parts [of the project] weren’t allowed,” Hartman said.

The port spent $10,000 in consultant services on submitting the application, Hartman told the commissioners.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at pgottlieb@peninsuladailynews.com.

More in News

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25