Port of Port Angeles to hold off on $3 million Terminal 1 project

PORT ANGELES — The Port of Port Angeles will delay the $1 million startup of a multiyear $3 million Terminal 1 pile-replacement project until 2015.

The project delay is among several 2014 capital-project delays and deferrals, port commissioners learned Tuesday.

In all, $1.4 million of the port’s $2.7 million 2014 capital budget has been deferred or delayed, Chris Hartman, port director of engineering, told commissioners as part of his second-quarter 2014 report, which covers January through June.

Schedule delays for the Terminal 1 and marine trades area cleanup off Marine Drive were based on permitting or coordination issues, Hartman said in a later email.

Deferred projects are being rescheduled to future years for such reasons as permitting agency staff turnover, complicated permitting requirements or other reasons, he said.

The $1 million in construction on Terminal 1 — where toxic, creosote-covered timber pilings will be replaced with stronger, environmentally safer steel piles — was slated to begin in October.

Now, it will begin in July 2015, Hartman said.

Construction must be completed by 2017, he said.

‘Still on track’

“We’re still on track there,” he told the commissioners.

The port already has spent $73,826 of $180,000 for redevelopment-permit costs and project design, Hartman said.

He said the Terminal 1 project holdup was due to permitting delays and, in part, turnover at the Army Corps of Engineers.

The permit also was a more comprehensive “full harbor programmatic permit” that outlined 10 years of anticipated improvements to other port’s piers rather than solely Terminal 1 improvements, he said.

“It looks at all our facilities and says, ‘In the next 10 years, we anticipate needing to do this many pile replacements at each of our facilities,’” Hartman said in an interview after Tuesday’s meeting.

Patricia Graesser, spokeswoman for the Corps of Engineers’ Seattle district, said Tuesday in an email that the permit covers maintenance activities at five terminals, including Terminal 1, and at log rafting areas and the Boat Haven marina.

The public comment period on the permit ended April 17.

“We are currently reviewing the project for compliance with the Endangered Species Act, tribal coordination and the National Historic Preservation Act,” she said.

The transit shed at Terminal 1, built in 1926 as the port’s first development, is eligible for the National Register of Historic Places and would be demolished, according to the public notice asking for comment on the project issued jointly by the Corps and the state Department of Ecology.

“It is not possible to predict a specific date for completion of the review and coordination process, as it involves entities outside the Army Corps of Engineers.

The improvements to Terminal 1, where 900-foot vessels dock for repairs and maintenance, will be funded in part with a $1.5 million U.S. Economic Development Agency grant that will not be endangered by the construction delay, Hartman said.

Terminal 1 was among two delayed and four deferred projects cited by Hartman in his presentation to the commissioners.

Marine trades area

A $250,000 cleanup project also will be delayed for the port’s marine trades area on Marine Drive near the site of the former Peninsula Plywood mill.

Funding was deferred for replacement of a security truck to allow for purchase of a more fuel-efficient vehicle in 2015.

Also deferred was an upgrade to the port’s virtual server, a fire-suppression upgrade for the port’s information technology room and acquisition of a gangway transition tower that would help cruise ship passengers disembark.

Port officials have borrowed a gangway system for this year’s cruises.

Projects completed include purchase of a $199,456 log loader.

The 23 projects still scheduled for 2014 include $160,000 in vehicle access improvements to William R. Fairchild International Airport, which is 75 percent complete and will be finished by mid-September, Hartman said.

They also include construction of a $100,000 stormwater treatment facility, which is 48 percent complete, he said.

“A number of projects are in planning stages or are moving toward construction now,” he said.

For eight of the projects still on schedule for 2014, nothing has been spent year-to-date, Hartman said.

Port security

In other action, port commissioners heard a report on a $701,063 federal grant to upgrade port security that was $67,336, or 9 percent, less than the $768,399 requested by the port for ID security, cybersecurity, camera and lighting improvements.

The port had applied for funding for 75 percent of the project cost of $1.02 million, with the port covering the remaining 25 percent, or $256,133.

The new project cost is $934,751.

The Federal Emergency Management Agency will decide by September “which parts [of the project] weren’t allowed,” Hartman said.

The port spent $10,000 in consultant services on submitting the application, Hartman told the commissioners.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at pgottlieb@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading