Port of Port Angeles’ schedule for KPly mill site cleanup advances; bids for project due July 8

Port of Port Angeles Commissioner Colleen McAleer ()

Port of Port Angeles Commissioner Colleen McAleer ()

PORT ANGELES — The Port of Port Angeles may know by mid-July who will clean up the former KPly mill site — and how the contractor will do it.

The port’s three commissioners Monday ratified their staff’s request for bids on the environmental project that’s expected to cost up to $5.4 million.

Bidders will have their choice of methods to clean the 19-acre area on Marine Drive just west of downtown:

■   Excavate and haul to a licensed landfill the soil that’s contaminated by gasoline, diesel fuel, hydraulic fluid, heavy oil, benzene, toluene, ethylbenzene, xylenes, pentachlorophenol, dioxins and furans. The dirt would be replaced with clean fill.

■   Use what’s called evaporative desorption to heat the soil, vaporize contaminants, recover the chemicals and render them harmless.

Both methods are acceptable to the state Department of Ecology, according to Chris Hartman, the port’s engineering director.

Which strategy will prevail will depend on its cost, with the lowest qualified bidder winning the contract.

“The deciding factor is going to be which one is more cost effective for our site,” Hartman said.

The project is moving ahead of schedule to start work before winter weather sets in, he said.

“That’s why the rush,” he said. “This property is highly valuable.

“The cleanup of this site has been a priority for the port since the mill operations ceased in December 2011” when the operation’s final manifestation, called PenPly, went bankrupt.

According to estimates Ecology shared at an open house in April, the cleanup could last up to seven months.

The port will host a pre-bid conference and site visit at 10 a.m. June 24. Deadline for bids is 2 p.m. July 8. The next regular port commission meeting is set for 9 a.m. July 14, when commissioners could award a bid.

The port will pay for the cleanup from its capital reserves and hope to recover costs from its insurers, from companies that contaminated the site, and if necessary, from funds left from a grant that paid for the PenPly mill demolition.

In other action Monday, commissioners increased from $192,000 to $232,000 the “not to exceed” limit on its contract with Carletti Architects of Mount Vernon to design the interior of the proposed Composites Recycling Technology Center, 2220 W. 18th St., at William R. Fairchild International Airport.

The expanded plans will include a solar-thermal hot water system, solar panels on the center’s roof, freezers to store the pre-impregnated carbon-fiber composite material the center will recycle, backup electrical power to the freezers and security controls.

The proposed center has attracted about $3.7 million in federal, state and Clallam County grants toward its projected $5.4 million cost. With the funds came opportunities to refine the design, said Hartman, producing the $40,000 increase.

In related action, Commissioner Colleen McAleer reported on the testimony she gave June 9 to a U.S. Senate committee on a bill to fund a study and demonstration project for composites recycling.

“It was great for our community to be able to highlight the work we’ve done in this innovative area,” she said.

Other testimony to the Senate Committee on Energy and Natural Resources included the Boeing Co.’s support of the study and demonstration project.

According to a staff member on the Senate Committee on Energy and Natural Resources, the Port Angeles center could receive some of the $10 million that Washington Sen. Maria Cantwell’s Bill 1432 would allocate for the study and demonstration.

_______

Reporter James Casey can be reached at 360-452-2345, ext. 5074, or at jcasey@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading