Port of Port Angeles delays its Maritime Trade Center design

Projected cost of 16,000-square-foot building over budget

PORT ANGELES — The Port of Port Angeles is stepping back for at least one year from pursuing a design of its Marine Trade Center project due to an unexpectedly high construction cost estimate.

Port staff recommended that port officials pause to look into additional funding sources to bring the project cost down.

“Staff does not recommend we continue with future phases of design until we can come up with a business case that would support the construction of the building,” Chris Hartman, director of engineering, told port commissioners on Tuesday.

The Marine Trade Center is envisioned as an industrial building capable of housing 175-foot vessels and the equipment necessary to haul these vessels out of the water for maintenance and repair.

The center also would house a multitude of marine trades as part of the Port of Port Angeles’ effort to expand maritime commerce.

The building would be constructed with pre-engineered steel with a single pitched roof while allowing space for a similar structure to be built in the future.

Port officials hired Carletti Architects as consultants to develop a design and associated construction cost estimate.

“We went in with a target construction cost budget of about $4 million as we worked with the consultants and we quickly learned that our idea of having a 30,000-square-foot building was not in the cards so we shrunk that down to about 16,000 square feet, designed in a way that it could be expanded to double that size in the future,” Hartman said.

Even after reducing the size, the estimated construction cost was $10.25 million, more than double the budget.

“So we went back to the consultant and asked for some engineering ideas of what could be removed to simplify and reduce the cost of the facility,” Hartman told commissioners.

“There’s a long list of items that we could remove. That cost estimate came back at $8.75 million,” he said.

Inflation and supply chain issues brought on by the COVID-19 pandemic and other national and international situations have played a significant role in the high cost, he added.

“There are numerous factors that have played a role in the increased cost estimates. There has been a 25 percent increase in construction costs across the state. Material supply chain impacts, supply and demand for federal and state funding, and shortage of available contractors are all drivers of this cost increase,” Hartman said.

In stepping back, port officials will look at state and federal funding opportunities that could close the gap in the budget and estimated costs.

That search may take a year or more.

“We’re going to be searching high and wide for any available funding programs and opportunities,” Hartman said.

“There has been an influx of federal funds from the infrastructure benefit bills that have passed recently, and we have been working really diligently on finding and applying for those.”

________

Reporter Ken Park can be reached at kpark@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading