Port of Port Angeles approves bid for $1.8 million wash-down facility

Connie Beauvais

Connie Beauvais

PORT ANGELES — A bid for the construction of a $1.8 million Marine Trades Industrial Park wash-down facility more accommodating than anticipated for larger vessels was approved Monday by Port of Port Angeles commissioners.

A $1.7 million bid construction bid submitted by McClure & Sons. Inc. of Mill Creek included the added feature of construction of a 175-foot-long wash-down pad for the self-service facility.

The $1.8 million total includes construction administration and bid-document revisions that had to be made after initial construction estimates came in too high.

The longer pad is nearly double the 93-foot length commissioners Connie Beauvais, Colleen McAleer and Steve Burke initially were considering and which would have required moving larger vessels during the wash-down process.

Steve Burke

Steve Burke

The winning bid included the supplemental footage McClure said could be built for $300,000 at the 19-acre Marine Drive site of the former K-Ply, then Peninsula Ply, plywood mills west of the downtown core.

That’s $100,000 less than the port staff’s estimate, “a good value,” port Public Works Manager Chris Rasmussen said in his report to the commissioners.

The target date is Oct. 31 for completing construction of the port’s second-largest capital project for 2018 at the undeveloped site.

“This is a critical investment,” Burke, the Port Angeles-area commissioner, said at the meeting.

“If we are going to commit to a marine trades investment to diversify jobs and revenue, then this is critical that we start doing this.

“We already have some people that can use it.”

Beauvais, the board president and West End-area commissioner, is “very much in favor” of the the bid, she said at the meeting.

“I would note, however, that this does not include any [wash-down facility effluent] treatment,” Beauvais said.

The initial construction estimate of $2.46 million by Reid Middleton engineering of Everett exceeded the $1.8 million budget by a “staggering” amount, port Director of Engineering Chris Hartman said in January.

Commissioners subsequently eliminated on-site wastewater treatment in favor of transporting it to the port’s Boat Haven marina on Marine Drive west of the Marine Trades Industrial Park.

“If we do get a lot of people who use it, it makes it worthwhile to consider doing the treatment,” Beauvais said Monday.

“That will be considered at another date.”

Mega-yacht shipbuilder Westport Shipyard on Marine Drive and Platypus Marine on North Cedar are expected to join new tenants at the industrial park in using the facility.

Platypus will be the main user at the outset for vessels that average 64 feet, Executive Director Karen Goschen said Monday in a later interview.

Westport builds 164-foot yachts.

“We know the volume of the larger vessels is a handful,” Goschen said.

“We have to wait and see how much usage we get and what that break-even point is to go to a different system.

“Platypus is the primary user because of how many boats they work on.

“Westport has a handful of warranty work, but they are mostly new-built.

“As we build out the marine trades park, there will be other users.”

Business interest in locating at the industrial park has been limited to representatives of smaller marine trades entrepreneurs, Goschen added.

“I wouldn’t call any of them right now at that large anchor-tenant level,” she said.

Bids rejected by the commissioners that included the longer wash-down pad were submitted by Interwest Construction Inc. for $1.9 million and Strider Construction Co. Inc. for $1.96 million.

Both are based in Burlington.

The wash-down facility has received state and city permits.

It will be funded with port capital improvement funds.

The port has applied for a state Community Economic Revitalization Board low-interest loan over 15 to 20 years with a 2.25 percent to 2.5 percent interest rate at a 50 percent port match.

The loan will be considered at a July 26 CERB meeting, with any costs incurred by the port before then used as part of the 50 percent match.

Project expenditures include $45,000 to revise the bid documents, $40,000 for construction administration and $5,000 for archaeological surveying-monitoring.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at pgottlieb@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading