Port Angeles to buy Rayonier tank, acreage for $995,000

PORT ANGELES — The City Council agreed Tuesday to buy a large tank on Rayonier’s former mill site and a portion of the property for $995,000, even though a purchase agreement had not been drafted.

The council’s vote of 6-1 — with council member Max Mania opposing the move — allows city staff to complete a purchase agreement with Rayonier Properties LLC, which includes the 11.86 acres of land around the 5-million-gallon structure, without coming back to the council for final approval.

The move gives the city a way to resolve its sewage overflow problem and room for expansion of its waste water treatment plant next to the 75-acre property.

The city will use the tank to temporarily store untreated sewage and storm water that would otherwise overflow into Port Angeles Harbor during heavy rainfall.

It would help the city come into compliance with a state Department of Ecology mandate that the city allows no more than one overflow at each of its four sewage outfalls a year beginning in 2016.

No finalized agreement

Staff did not have the finalized agreement available for council review because the terms of agreement for a purchase — which includes a commitment from Rayonier that the city will be indemnified for the environmental cleanup of the land — were not sorted out between the city and the company until Monday, said City Attorney Bill Bloor while apologizing for the position the council was put in.

But he urged the council could not wait because the city must have ownership of the tank by the end of the month to remain on schedule with complying with Ecology’s mandate.

A document may not be finalized for another two weeks, and that put the city at risk of missing that deadline if it was brought back to the council, he said.

Bloor also said the terms of the agreement, also approved by the council Tuesday, will not be changed.

Those terms give the city the property and rights of way it needs to use the tank and keeps it from paying for cleanup of the land.

Mayor Dan Di Guilio and City Council member Cherie Kidd expressed concerns with not having the document ready, but supported the move due to the need to have ownership by the end of the month.

“We’re up with our backs against the wall,” Kidd said.

Mania maintained his opposition against the use of the tank.

Mania said the city should look at other options, such as mandating the disconnect of roof drains from the sewer system and forms of development that prevent water run off.

“In my mind, the idea of using the Rayonier tank is an outdated business-as-usual approach,” he said.

“Prevention is always better than treatment,” he added.

Public comment

Three people spoke during public comment either against the use for the tank or encouraged the city to reduce overflows by focusing on disconnecting storm water from the sewer system and promoting “low-impact development.”

Darlene Schanfald of the Olympic Environmental Council, who has been a frequent critic of the plan, said that the solution is too shortsighted and doesn’t fully resolve the sewage overflow issue.

She encouraged the council to look for other solutions, including the reuse of storm water rather than just treatment.

“You have the chance to be leaders, to join others in Washington state, the nation and the world,” she said, “to recycle rain water, to naturally clean storm water, beautify the area by using sustainable methods, to be a role model on how much you can educate its public using long-term sustainable storm water handling methods.”

City Manager Kent Myers promoted the use of the tank as an economical and expedient way to meet Ecology’s deadline.

“The use of the tank is the method that is most beneficial to the harbor and has the least expense to our citizens,” he said.

Myers also said the city is beginning to further promote its discount for homes that disconnect downspouts from the sewer system.

He also said it prevents new roof drains from connecting to the sewers.

The city was expecting the Harbor-Works Development Authority to acquire the tank for it.

The city decided to move for acquisition of the tank itself when became clear earlier this summer that negotiations between Rayonier and the public development authority for a sale of the former mill site began to falter.

While city staff say the tank is not large enough to prevent every overlfow, it is expected to put the city in compliance with Ecology’s mandate.

Price tag

The city estimates the total price tag of that solution will be about $38 million to $42 million.

Steve Sperr, city deputy engineering director, has said disconnecting the stormwater pipes and roof downspouts from the sewer system would cost about $80 million to $90 million.

City utility customers are paying a $10.25 per month fee to cover the costs of the sewage overflow project. That rate, established about five years ago, will increase about $2 a year until 2015. But utility customers will pay the fee for another 20 years.

Approximately 32 million gallons of untreated effluent is dumped in the harbor ever year.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading