Port Angeles smart meter project hits snags, delayed

PORT ANGELES — More than eight months ago, the city of Port Angeles embarked on a $5.4 million project to replace its utility meters with computerized versions, called smart meters.

The project, approved in December 2010 and started last June, was supposed to be wrapped up last month, but few homes have received them.

The city and its contractors are grappling with how to make the system work.

The trouble, city Deputy Power Systems Manager Larry Dunbar said, is making sure the computers at City Hall communicate properly with the equipment in the field.

“We’re integrating these two systems, and it’s proving to be more time-consuming and challenging than we planned for in the schedule,” he said.

The new meters allow water and energy use to be read remotely at City Hall through wireless devices and fiber-optic cables.

Last summer, the city had 1,000 electrical and 1,000 water meters replaced to test the system as part of the project’s first phase, which remains incomplete.

The last of the city’s approximately 19,000 meters were supposed to be replaced in January.

Dunbar said other utilities have come across similar problems, and he is hopeful it can be resolved in about two months.

The goal is to finish the project by the end of the year, he said.

So far, the delay has not affected the cost of the project, and Dunbar said he doesn’t expect it will have an impact.

But as a result of the delay, the City Council on Feb. 21 approved an $850,000 payment to the city’s contractor, Mueller Systems, that was supposed to come after the completion of the project’s first phase.

Dunbar told the council the city is still withholding half of its payments to Mueller until the phase is completed but said the payment approved Feb. 21 was justified since both parties have contributed to the delay, and the company has had to stretch its dollars longer than anticipated.

“Mueller has taken longer in some areas, and the city has taken longer in some areas,” he said.

Phase one also has been expanded to include the installation of another 2,000 meters.

The council approved the move unanimously, though a couple of council members expressed reservations.

Mayor Cherie Kidd said she was “uncomfortable” with approving more funds to be spent when the project remains stalled.

“I question the wisdom of what we are doing,” said Councilman Brad Collins.

Dunbar said city staff members remain confident about the technology.

“We told everyone at the beginning what everyone was telling us: that this will be the hardest, and this is the hardest part,” he said.

“This is what everyone struggles with.”

The new meters, which are said to be more accurate, not only will allow the city to read electricity and water consumption remotely, but will allow residents to track their consumption throughout the day, rather than receiving a total figure at the end of the month.

_________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading