Port Angeles seeks state loan on sewer outfall project

PORT ANGELES — City public works staff hope to get a $12 million state loan for the second phase of a multimillion-dollar effort to reduce the amount of sewage and stormwater that flows into Port Angeles Harbor during heavy rains.

City Engineer Mike Puntenney expects to hear this summer whether the city’s application to the state revolving loan program, administrated by the state Department of Ecology, is accepted.

The city’s combined sewer overflow, or CSO, reduction projects will cost about $18.5 million overall, Puntenney estimated, factoring in design, construction and construction management expenses.

Ecology officials have told him the city’s loan application is a high priority, he said.

Ecology spokeswoman Sandy Howard said a final decision is expected July 1.

“It’s looking very good [for Port Angeles’ application],” Howard said.

The city would repay the loan at roughly 2.7 percent interest over 20 years, Puntenney said.

If the loan is approved, the city expects to go out for bid on the project in August.

If it is not, Puntenney said, the city will continue to apply for low-interest state loans, adding that Ecology — which is requiring the projects, threatening fines — understands that completion is contingent upon the city getting such a loan.

CSO utility charge

Funding also will come from money accumulated through a CSO charge on city resident utility bills. The amount for an average residential customer is $20.10 monthly.

The overall goal of the city’s project is to increase sewer and stormwater capacity between downtown and the city’s plant, and reduce the amount of untreated sewage and stormwater flowing into Port Angeles Harbor during heavy rains.

The last time that happened was in early March, when some 6 million gallons of combined rain water and raw sewage flowed into Port Angeles Harbor because rain overwhelmed the sewer system.

Second phase

The second phase will include an upgraded pump station to be built near the beginning of Marine Drive and pipes to connect the station with the pipes added earlier underneath Oak Street as part of the $16.7 million first phase of the project, Puntenney said.

On Tuesday, the city’s Utility Advisory Committee recommended full City Council approval of a $1.56 million contract with Bellevue-based Vanir Construction Management to manage the construction contractor that will be selected for phase two.

The city contracted with Vanir to manage construction of phase one.

Phase one work included retrofitting a 5 million-gallon storage tank the city bought on the former Rayonier mill property to hold untreated stormwater and sewage during heavy rains until it can be treated in the city’s wastewater-treatment plant near the former mill site.

Council members are expected to vote on the construction management contract at a meeting that will begin at 6 p.m. Tuesday at City Hall, 321 E. Fifth St.

________

Reporter Jeremy Schwartz can be reached at 360-452-2345, ext. 5074, or at jschwartz@peninsuladailynews.com.

More in News

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25