Port Angeles: No graving yard restart for at least a week; state considering alternate locations

PORT ANGELES — Work on the state Department of Transportation’s $17 million graving yard on Marine Drive won’t resume for at least another week.

State officials won’t estimate the cost of the work stoppage or how the delay will impact completion of the $204 million Hood Canal Bridge replacement and retrofit project.

But preliminary cost estimates could be available today.

Work was halted Aug. 26 after Native American remains were found at the 22.4-acre construction site where anchors and pontoons will be built to replace the eastern half of the floating bridge.

Representatives of the Lower Elwha Klallam Tribe and Transportation met for about six hours Wednesday afternoon, trying to reach an agreement that will get work started.

Another meeting is scheduled for Sept. 11 at the tribal center, west of Port Angeles.

The tribe’s main concern is preventing further disturbance of Native American remains that might be at the site.

Transportation Communications Director Linda Mullen said the department does not want to leave Port Angeles, but must look at all possibilities — including relocating.

—————–

The rest of the story appears in Thursday’s Peninsula Daily News.

More in News

U.S. Rep. Emily Randall.
US Rep. Randall speaks on House floor about insurance

Example of fictional family shows premium increase of more than 1,000 percent

Spending patterns led to pool audit

Office identifies $33K in unsupported payments

Comments oppose plan against Port Townsend zoning changes

Option would increase maximum limit on units per 40,000 square feet

x
Sequim program uses grant for utilities, rent

Community support through Peninsula Home Fund gives $10,000 to organization

Firefighters Tyler Gage and Tatiana Hyldahl check out the light connections on the 1956 fire truck that will travel the streets of Port Angeles during the 41st Operation Candy Cane beginning Monday. Santa and his helpers will pass out candy canes to those who donate food items or cash. The runs will begin at 5:30 p.m. and include the following areas: Monday, west of I street and M street; Tuesday, I and L streets to C street; Wednesday, C Street to Lincoln Street; Thursday, Chase Street to Chambers Street; Friday, Jones Street to Golf Course Road; Dec. 13, above Lauridsen Boulevard. It will be stationary from 5:30 p.m. to 7 p.m. on Dec. 14 at the Port Angeles Grocery Outlet and during the same time on Dec. 15 at Lower Elwha Food and Fuel. (Dave Logan/for Peninsula Daily News)
Operation Candy Cane

Firefighters Tyler Gage and Tatiana Hyldahl check out the light connections on… Continue reading

Online survey launched for Sequim parks access

The city of Sequim has launched an online survey to… Continue reading

Crews work to remove metal siding on the north side of Field Arts & Events Hall on Thursday in Port Angeles. The siding is being removed so it can be replaced. (Dave Logan/for Peninsula Daily News)
Siding to be replaced

Crews work to remove metal siding on the north side of Field… Continue reading

Tsunami study provides advice

Results to be discussed on Jan. 20 at Field Hall

Chef Arran Stark speaks with attendees as they eat ratatouille — mixed roasted vegetables and roasted delicata squash — that he prepared in his cooking with vegetables class. (Elijah Sussman/Peninsula Daily News)
Nonprofit school is cooking at fairgrounds

Remaining lectures to cover how to prepare salmon and chicken

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects