Port Angeles: Graving yard archaeology to continue into at least November

PORT ANGELES — When the archaeological excavation of the graving yard began in April, no one involved thought the process would continue into November.

The excavation was through to take four months to complete.

But as September comes to a close and the second target date — Sept. 24 — passes, workers continue to find human remains and artifacts on the 22.5-acre site of the huge onshore dry dock for the Hood Canal Bridge replacement project.

“The village is a lot bigger than anyone ever anticipated, and we have found more than anyone thought we would,” said Lower Elwha Klallam Tribal Chairwoman Frances G. Charles.

“We continue to find ancestral remains and artifacts at the site, and continue to work as fast as we can to finish the excavation.”

The site, located along Marine Drive on the Port Angeles waterfront, is the former home of one of the largest documented Klallam villages, named Tse-whit-zen.

Scientific tests have shown the village to be at least 1,700 years old, and archaeologists working on the project say Tse-whit-zen is one of the largest villages uncovered in the Northwest.

Project on schedule

Despite the longer excavation process, state Department of Transportation officials say the eastern half of the floating bridge is on schedule for replacement in May 2007.

“There are so many things that we can juggle to keep this project on schedule,” said Transportation’s Olympic Region spokesman Lloyd D. Brown.

“There are so many innovative people working on this project who have developed ways for construction to happen while still respecting the archaeology.”

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading