Port Angeles’ First Street project ahead of schedule, city says

PORT ANGELES — The First Street stormwater project is well ahead of schedule and could be done by May 24, said the city of Port Angeles’ lead engineer.

The contractor, Road Construction Northwest Inc., was initially scheduled to be done in mid- to late June.

“We’re looking to be completely done the week before Memorial Day,” said city engineer Mike Puntenney. “We’re blazing.”

Since starting about a month ago, RCNI has finished placing a new stormwater pipe under the south lane of First Street between Valley and Oak streets.

Paving plans

Next, the Renton-based company will pave that section of the road.

Puntenney said that should be done by the end of the week.

From Oak Street, work crews will continue installing the pipe eastward to Laurel Street.

Before finishing, the north lane of the road between Valley and Laurel streets will be repaved, bike lanes will be added, and crosswalks will be replaced.

The south lane of First Street between Laurel and Lincoln streets also will be repaved. Fog seal will be applied to the north lane of that block.

The project has a price tag of about $2.25 million, according to the city, with the city contributing $225,000 for street paving and the rest coming from the National Park Service.

The park service is covering that cost because the project is part of its $324.7 million Elwha River Restoration Project, the goal of which is to restore salmon habitat.

The First Street project is intended to remove enough stormwater from the city’s sewer system to offset the contribution of sewage from the Lower Elwha Klallam reservation.

The tribe will be connected to the city’s sewers because it’s expected that its septic tanks will become unusable as the groundwater level rises as a result of the removal of the two Elwha River dams.

The removal of the 108-foot Elwha Dam and the 210-foot Glines Canyon Dam is to begin in September and be finished in three years.

The park service agreed to fund a stormwater disconnect project to offset the impact on the city’s sewage overflow problem.

Construction of the sewer system was expected to begin earlier this month but is on hold for between 30 and 60 days.

It’s expected to be finished in July or August 2012.

The delay won’t affect the First Street project, said Glenn Cutler, city public works and utilities director.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading