Port Angeles council updated on progress of new City Light building

Lease renewed for temporary facility

PORT ANGELES — The city of Port Angeles has renewed a lease with Atlas Trucking Co. to house the light operations division until the nomadic city department moves into a permanent home.

The City Council voted 7-0 Tuesday to approve a two-year, $184,000 lease with Atlas for a 5-acre site in west Port Angeles.

The action will allow light operations to continue to use the temporary facility until the city constructs a $6.4 million light operations building at the public works equipment storage yard near the corner of West Lauridsen Boulevard and the Tumwater Truck Route.

On schedule, budget

“We are at 30 percent design,” Port Angeles Public Works and Utilities Director Thomas Hunter said of the new building Tuesday.

“We are on schedule and we are on budget.”

The new light operations building is scheduled to be completed before 2022.

“I do think it’s worth reiterating we have been anticipating this and putting money in reserves for this and that it does meet the council directive of no new debt,” Mayor Kate Dexter said.

Port Angeles light operations, a division of the public works and utilities, has been housed in several locations since the 1980s.

The former Port Angeles City Light building at 240 W. Front St. was declared surplus in 1987 for a higher and better use that complemented the downtown corridor, city officials said.

In 2007, the Front Street building was sold to Family Medicine of Port Angeles, now North Olympic Healthcare Network, for $775,000.

After the sale of the downtown building, City Light moved to a Port of Port Angeles-owned building near William R. Fairchild Memorial Airport.

In November 2017, the port told the city to vacate the leased site to make room for an expanding commercial business by May 31, 2018, according to city documents.

The City Council in March 2018 agreed to lease the 5-acre site owned by Atlas Trucking at 1734 W. U.S. Highway 101 for about $90,000 per year.

“It’s a great price for that property,” said first-year City Council member Charlie McCaughan, a Clallam County Public Utility District procurement and facilities supervisor.

“Being a former employee of the light op, I understand the history and what’s gone on there.”

Hunter said he would update the City Council on the new building when it is 65-percent designed.

He added that the new light ops building would be about 6,000 square feet smaller than the temporary facility but designed with proper ingress and egress for light operations.

The Atlas site has about 16,000 square feet of enclosed space and about 9,200 square feet of covered space, Hunter said in a memo.

The new light operations building will have about 18,777 square feet of enclosed space.

“It’s a great project,” Hunter told the council.

In other public works news, the council awarded a $278,055 contract to Dutton Electric Company, Inc. of Lynnwood for electrical switchgear upgrades at the Laurel Substation.

”The contents of this project are relatively technical,” Hunter told the council.

”I think it’s important to note that this is one of five substations that we need to replace the switchgear at.”

Hunter said the awarded contract was well under the $500,000 budgeted for the project.

“That is an opportunity for us to give tremendous kudos to the engineering division in light operations because they really worked with some efficiencies, opened up that substation, had people come in and present alternatives as to how we can do things a little bit more efficiently,” Hunter said.

“Ultimately, we got a better project price because we went through that process.”

City Finance Director Sarina Carrizosa said the savings will be applied to other projects in the capital facilities plan.

“I really appreciate what I see as some very significant shifts in creative problem solving in public works,” Dexter said, “and I think the city is going to be significantly better off for that.”

In other discussion, the council reviewed its 2019-2020 strategic plan and voted to make minor modifications in a February work session.

The existing strategic plan has three main objectives:

• Preserve long-term economic, ecological and social well being while demonstrating innovative and desirable urban design principles.

• Build financial capacity to provide consistent, quality municipal services and infrastructure improvements.

• Exemplify excellence in government and community leadership.

“This strategic plan sits as a two-year action plan for the comprehensive plan,” Council member Lindsey Schromen-Wawrin said.

“We spent some time with the objectives goals and strategies last year. If those are something that work well for the new council members, then that’s a really good sign.”

Four new members joined the seven-member council this month: McCaughan, Navarra Carr, Brendan Meyer and LaTrisha Suggs.

“I just want to warn the council this is a big project and I’m ready for it, but it’s going to require us to get down to details very quickly,” council member Mike French said.

________

Reporter Rob Ollikainen can be reached at 360-452-2345, ext. 56450, or at rollikainen@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading