Port Angeles bridges on schedule, officials say

PORT ANGELES — The Eighth Street bridges will open in February, say project managers, who say the final touches are being done on the replacement spans.

“We realize it doesn’t look like a lot is getting done,” said Greg Bennett, Parsons project manager.

“It’s a lot of little things that you don’t see, day in and day out, when they are getting done.”

Steve Sperr, city engineer, said on Friday that the contractor, Parsons RCI of Sumner, is contracted for working days until about Feb. 15.

By then, he said, the project will be finished.

Glenn Cutler, city public works director, said in November that the $24.6 million project to replace the Tumwater Creek and Valley Creek bridges would be completed about Feb. 2.

The bridges were initially scheduled to open in November.

Construction began on June 25, 2007, and traffic was rerouted through Port Angeles to avoid the major arterial that crosses two ravines — leaving thin traffic passing by businesses on Eighth Street between the two spans.

Soil problems

Cutler has said that poor soil on the west side of the Tumwater Creek bridge required a redesign of a foundation abutment that resulted in extending Parsons’ contract for 45 working days.

The extension cost the city $90,000.

The project is funded by $21.6 million in state Department of Transportation grants and $3 million in city funds.

With a February opening, the bridge replacement project will have taken 19 months in total, which is the duration the city estimated when it put the project to bid in December 2005.

Ingo Goller, Exceltech construction manager, said in November that the Tumwater Creek bridge was about 90 percent completed and the Valley Creek bridge was about 85 percent done.

Exceltech has a $1.94 million contract with the city to manage the project.

The concrete bridges are 47 feet wide with two 12-foot lanes, two 5-foot bicycle lanes, two 6 1/2-foot sidewalks and two pedestrian viewpoints.

Minimal staff

Bob Alton, Exceltech office engineer, said on Friday that work continues on the bridge, although it may not be very visible.

Alton said the final work on the bridges doesn’t require a lot of manpower.

Alton and Bennett said the work that is left to complete includes painting a pigmented sealer on the concrete for weather protection, placement of the handrails, wetland and other site mitigation.

“It’s all the finishing up activities,” Bennett said.

“There is limited amount of work to get done. We only need the people that support that limited amount of work.”

Bennet added that the company wants to make sure that all of the small items are done before the bridges are opened.

Alton said crews were unable to work on the bridges on six days last month because of bad weather.

Bennett said sunny, dry weather is needed to finish spraying the sealer.

Because of poor weather on Friday, workers had to stop prepping the bridges for the sealer at noon, he said.

“It’s weather dependent,” Bennett said. “It’s a tough one to battle with.

“Just ask for warm weather and a few weeks of patience and we’ll get there.”

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@ peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading