PORT ANGELES — The project comes with a hefty price tag: $40 million.

But city Engineer Mike Puntenney said Tuesday evening that the city’s plan to solve its sewage overflow problem by using a large storage tank is the right choice for Port Angeles.

“That’s a lot of money,” he acknowledged, while speaking to about 30 people in the council chambers at City Hall. “It can’t be taken lightly.

“The question is: Can you do this cheaper and solve the problem?”

His answer was no.

Puntenney gave an hourlong presentation at the public meeting aimed at making the case for the city and responding to criticism of the project from some environmentalists.

The sewage spills are caused by stormwater overflowing the sewer system.

It’s a problem many older cities face since the solution for sewage and stormwater 100 years ago was to dump it all into the same pipes.

To solve the problem, which it must do under the federal Clean Water Act, the city is going to use an existing 5-million-gallon tank it acquired from Rayonier Inc. to temporarily store untreated effluent during heavy rainfall when the sewer system surpasses its capacity.

Additional sewer lines will be built from downtown to the tank, located next to the wastewater treatment plant, and improvements to the plant and pumping stations will also be made.

Opposition

But the Olympic Environmental Council has a different view and has criticized the city for not using what it sees as “green” solutions.

The environmental council said the city needs to eliminate the problem at the source by removing stormwater from the city’s sewer lines.

But that solution is not as simple as it seems, Puntenney said.

With that method, the city would have to not just remove stormwater from the sewers, it would also have to expand its stormwater system to handle the additional runoff, he said.

That would also result in construction throughout the city, rather than just along the waterfront, Puntenney said.

And it would only solve about 60 percent of the problem, the engineer added.

About 40 percent of the overflows is caused by water seeping into the aging sewers underground and through manholes.

Altogether, Puntenney estimated that solving the problem by disconnecting the stormwater and sewer lines, building new stormwater pipes and sealing the sewers would cost about $180 million.

It would also take longer to complete, he said; the city is required by the state Department of Ecology to solve the problem by Dec. 31, 2015.

Darlene Schanfald, spokeswoman for the OEC, said after the meeting that she thought the city’s estimate was a bit high, though she didn’t dispute that the solution favored by the group would cost more.

But she noted it would involve work the city may find itself needing to do anyway, such as repairing and sealing aging sewer pipes and manholes and expanding its stormwater system, which is already undersized.

“If you do that, it’s more sensible in the long term and sustainable,” Schanfald said.

“We need another mentality,” she added.

Earlier this year, the group dropped an appeal of the project.

Schanfald said the group still plans to challenge the project, but she declined to say how.

Drain spouts

The Olympic Environmental Council, a coalition of groups on the North Olympic Peninsula, also has urged the city to focus on disconnecting roof drains from the sewer systems.

Puntenney said the city encourages residents to use rain barrels or let the water flow onto their yard when possible, but he noted it wouldn’t do enough to solve the problem.

Additionally, he said, much of the soil in Port Angeles drains poorly, meaning that residents who do disconnect their down spouts would either have to tie into the stormwater system, which has its own capacity issues, or use rain barrels.

The project is expected to get under way in April or May, when new sewer pipes are slid through the city’s industrial waterline, which runs parallel to the Olympic Discovery Trail.

That work will stop before the North Olympic Discovery Marathon in June, Puntenney said.

Construction downtown at the intersections of Lincoln Street and Railroad Avenue and Oak Street and Railroad Avenue will begin around October 2012.

The project is expected to be finished in late 2015.

The level of overflows, which includes both sewage and stormwater, varies widely year by year.

In 2001, 1.78 million gall­ons was released, while 2006 saw 75.5 million gall­ons get dumped.

On average, about 32 million gallons is released each year.

For more information, visit www.cityofpa.us/CSO.htm#CSOsp.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25