Port Angeles 10th Street work slow but steady

PORT ANGELES — Crews are making “steady progress” on 10th Street reconstruction in west Port Angeles despite periods of rain, a city engineer said Wednesday.

“We see the light at the end of the tunnel,” added Jonathan Boehme, civil engineer and project manager.

“We are on track to be mostly completed by the middle of December.”

Lakeside Industries of Port Angeles and its subcontractors are rebuilding a 0.6-mile segment of West 10th Street between N and I streets under a $2.5 million contract with the city. Boehme said the project remains on budget.

City officials hope to have the work substantially completed by Dec. 21.

“The contractor, Lakeside, is working very hard to get this project completed as fast as they can,” Boehme said.

Final touches

After a winter break, crews will return when the weather improves — most likely in April — to add a final 2-inch layer of asphalt and paint the road markings, Boehme said.

Bicycle lanes will be added to both sides of the road and a sidewalk between N and I streets will be constructed to improve safety for pedestrians and students walking to and from Hamilton Elementary School.

The 10th Street project began in July with a targeted completion of late October.

An August strike by Local 302 of the International Union of Operating Engineers in Western Washington slowed the 10th Street project and several others on the North Olympic Peninsula.

“It affected a lot of subcontractors,” Boehme said.

The 17-day strike, which had a major impact in Seattle, ended Sept. 6.

Before the 10th Street project winds down, crews will grade the widened road west of M street, install a water main along M Street, pour concrete for portions of the sidewalk and replace concrete driveway entrances.

A 2-inch base layer of asphalt will be installed and temporary striping will be painted before the winter hiatus.

“It is very much weather dependent, this final stretch,” Boehme said.

The city received a $1.25 million state grant to help rebuild the crumbling section of 10th Street.

The city matched the grant with $504,999 in voter-approved Transportation Benefit District funding and $145,000 in real estate excise taxes. The rest of the expense will be covered by stormwater and water utility funds, according to city documents.

City voters in August 2017 approved a 0.2 percent sales tax increase to fund the Transportation Benefit District. West 10th Street was the first use of TBD funding.

The next TBD-funded projects will be chip seals for road preservation and a new asphalt surface for East Lauridsen Blvd. between Lincoln and Race streets, Boehme said.

For updates on the 10th Street project, go to the city’s website, www.cityofpa.us.

________

Reporter Rob Ollikainen can be reached at 360-452-2345, ext. 56450, or at rollikainen@peninsuladailynews.com.

A barricade marks part of the construction zone along West 10th Street at South M Street in Port Angeles on Wednesday. (Keith Thorpe/Peninsula Daily News)

A barricade marks part of the construction zone along West 10th Street at South M Street in Port Angeles on Wednesday. (Keith Thorpe/Peninsula Daily News)

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading