Point Hudson breakwater opens centennial celebration

$12 million port project finishes on time, under budget

Government officials applaud the ribbon cutting at the Point Hudson breakwater in Port Townsend on Wednesday afternoon. (Diane Urbani de la Paz/For Peninsula Daily News)

Government officials applaud the ribbon cutting at the Point Hudson breakwater in Port Townsend on Wednesday afternoon. (Diane Urbani de la Paz/For Peninsula Daily News)

PORT TOWNSEND — It was appropriate that Commissioner Carol Hasse wielded the oversized scissors at the ribbon-cutting ceremony to celebrate the completion of the Port of Port Townsend’s breakwater project at Point Hudson.

Standing on the bow of the 72-foot-long Saratoga on Wednesday, the sailmaker snipped the red, white and blue ribbon — remnants of spinnaker sailcloth — hanging between the new south and north breakwaters that protect the 50-slip marina.

It had been Hasse’s idea to use leftover pieces of sailcloth for the ceremony.

“That way it’s re-used and it speaks to our marine heritage,” said Hasse, who operated Hasse & Co. Port Townsend Sails for 43 years until she retired in 2021. “But I had no idea I was going to cut it until [Executive Director] Eron [Berg] passed the scissors to me.”

The celebration also marked the start of the port’s centennial; in 1924, Jefferson County voters approved the creation of a port district that encompasses the entire county.

More than 60 people who were involved in or supported the breakwater project rode the Saratoga, one of Commission President Pete Hanke’s four Puget Sound Express whale-watching boats, from the port’s offices to Point Hudson. Among the passengers were U.S. Rep. Derek Kilmer, D-Gig Harbor; state Sen. Kevin Van De Wege, D-Lake Sutherland; state Reps. Mike Chapman, D-Port Angeles, and Steve Tharinger, D-Port Townsend; as well as Port Townsend city officials and Jefferson County commissioners.

“This a great way to celebrate how important the maritime sector is to our region, not just historically but going forward as well,” said Kilmer, who helped secure federal funding for the project. “This is a community that knows how to get everybody’s oars in the water and row in the same direction.”

Replacing the two aging breakwaters had been on the port’s list of priorities for a long time, Hanke said.

“This 12-year endeavor was at the top of everyone’s list and for many years it looked dubious,” he said. “The costs kept going up.”

Hanke thanked Berg — the fourth executive director he’d worked with during his 11 years on the commission — Deputy Director Eric Toews and Capital Projects Director and Chief Engineer Matt Klontz for their roles on the project.

Commissioner Pam Petranek said maintaining the infrastructure of Port Townsend’s working waterfront is integral to its economy and culture.

“These structures are critical; without the jetty, it’s over,” Petranek said. “In 2018, marine trades made up 20 percent of the jobs, and marine trade wages were 23 percent higher than other jobs.”

Constructed in the 1930s, the breakwaters had been repaired over the years, but they suffered significant damage during winter storms and a king tide in the winter of 2018-19. The schedule for their removal and replacement was constrained by fish protection work windows that dictated when in-water activity could occur in addition to the annual Wooden Boat Festival that takes place the first weekend in September.

But the two-year, $12.14 million project was completed on time and under its original $14.1 million budget.

More than half of the funding came from a $7.1 million U.S. Department of Commerce Economic Development Administration grant. Another $2.5 million came the state’s capital budget, with additional funding from a U.S. Fish & Wildlife Service BIG Tier 2 grant and the port’s voter-approved Industrial Development District levy. The unspent funds will stay in the port’s IDD budget for investment in future projects.

The funds raised by the IDD, which voters approved in November 2019, have been crucial in leveraging federal and state dollars for the breakwater and other port projects, Berg said.

“The IDD makes us eligible for projects with matching funds,” he said. “It shows the community’s support and commitment.”

The port’s goal is to translate the $17 million in IDD funds that will be raised over the course of the levy into $50 million in capital projects, he said.

Mott McDonald led engineering on the project and Tom Coultas acted as resident engineer. Orion Marine Contractors were the construction partner, Widender & Associates coordinated and managed environmental permitting, and Cowling & Company handled environmental monitoring.

The port currently has 32 capital projects in various stages of planning and execution, including repairing the breakwater at Boat Haven Marina and expansion of the boat yard, construction of a new Gardner boat ramp, improvements at Herb Beck Marina, industrial development at the Jefferson County International Airport and planning for future use of Short’s Farm.

Breakwater amenities

The completed breakwater project has two elements that can be appreciated by those who don’t own a boat.

One is the new walkway along the top of the south jetty that juts into Port Townsend Bay and is already proving to be a popular with pedestrians.

The other is an underwater camera that live streams from a site near the entry to the marina. Installed and monitored by Randy Williams of the Washington Scuba Alliance, the camera is directed at a reef created last summer from riprap from the old north jetty where members of the alliance relocated 400 invertebrates so they wouldn’t be crushed during construction.

To watch the live stream, go to tinyurl.com/4h6ep2ex.

________

Reporter Paula Hunt can be reached by email at paula.hunt@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading