Staff with PNNL-Sequim plan to expand the laboratory space by demolishing two temporary buildings by Washington Harbor along Sequim Bay and build a three-story structure. They also intend to add Sequim utilities along West Sequim Bay Road in the coming years. (Andrea Starr/Pacific Northwest National Laboratory)

Staff with PNNL-Sequim plan to expand the laboratory space by demolishing two temporary buildings by Washington Harbor along Sequim Bay and build a three-story structure. They also intend to add Sequim utilities along West Sequim Bay Road in the coming years. (Andrea Starr/Pacific Northwest National Laboratory)

PNNL-Sequim expansion linked to West Sequim Bay Road utility additions

City water, sewer improvements could go to bid mid-2025

SEQUIM — Funding is secured and planning is underway to expand the Pacific Northwest National Laboratory in Sequim, the Department of Energy’s only marine and coastal research lab.

T.J. Heibel, renewable energy lead for PNNL-Sequim, said planners and researchers are working to design new engineering and technology lab space by Washington Harbor along Sequim Bay.

Two temporary marine science lab buildings on the west shoreline will be demolished to make room for a three-story building with a tall bay area for larger projects.

“Marine energy research equipment is huge, and we need it in a controlled environment,” Heibel said.

The upper and lower PNNL-Sequim campus currently hosts nearly 15,000 square feet of research space for about 100 staffers.

“We want it to be a lasting asset that serves the nation,” Heibel said of PNNL-Sequim.

Additional improvements include updates to the shoreline infrastructure with more smaller rectangular seawater tanks to replicate testing scenarios and build confidence in research results, he said.

They’ll also update the dock to better accommodate the $4.55 million RV Resilience, a first-of-its-kind hybrid research ship.

At the Sept. 5 ship dedication, U.S. Sen. Maria Cantwell, D-Edmonds, said she helped secure nearly $21 million for PNNL-Sequim’s expansion to “build prototype marine devices and instruments to go on research vessels just like the one we’re dedicating today.”

“This partnership here at Sequim is very critical to our nation,” Cantwell said, as Washington state’s coastal sectors employ more than 2 million people and contribute more than $40 billion to the state and $400 billion to the state economy.

Cantwell and PNNL staff said other planned investments at PNNL-Sequim include a pre-permitted marine testing site, an underwater cabled array connecting at-sea devices to shore facilities, and an onshore microgrid and battery storage system.

Utilities

Another key element to PNNL-Sequim’s expansion includes bringing utilities from the Sequim to the laboratories.

Heibel said part of the secured funds will help PNNL-Sequim pay to install pipelines from West Sequim Bay Road to the campus. They will keep an artesian well for research purposes because the water is so clean, he said.

Discussions to bring utilities to the campus have been a talking point for decades, PNNL-Sequim staff said.

Nick Dostie, Sequim’s city engineer/deputy director of public works, said city staffers are in discussions with PNNL about a future annexation as they plan to bring utilities to the site.

PNNL’s utilities will connect to a project called the West Sequim Bay Corridor Improvements — about $16.3 million in projects, included in the city’s Capital Improvement Program for 2025-2030.

Dostie said that will bring city utilities to the corridor for the first time and allow for full build out of the area’s lots/parcels for sewer, while water will need to be extended farther down the corridor at a later date.

The new service area will include 350 acres of R4-8 (residential) zoning, 170 acres of Planned Residential Community zoning and 90 acres of high-tech light industrial zoning.

The corridor project will go along West Sequim Bay Road from Washington Harbor Road to Forrest Road for sewer utilities, and from Independence Drive to Junco Road and Washington Harbor Loop for water utilities.

The city purchased a parcel at Forrest Road for $70,000 in June 2023 to host Sequim’s largest lift station designed for full build out of the service area, Dostie said.

City staff plan to go to bid for the project in the second or third quarter of 2025, he said, with construction possible in the first quarter of 2026, and pipeline and lift station construction complete in the third or fourth quarter of 2028.

When construction tentatively begins on the project, Dostie said portions of West Sequim Bay Road will be closed to through traffic with only local access available.

Funding for the corridor project comes through the Department of Ecology Small Community Project Priority List as a partial loan and partial grant, where the city cannot receive more than 12 percent grant funding, Dostie said.

Sequim also is seeking funding from PNNL and other applicants benefiting from the new sewer lift station, he said.

The laboratory sits on the S’Klallam village site of sxʷčkʷíyəŋ, which was purchased by Hans Bugge in 1899 and used as The Bugge Cannery until 1966. Six years later, a fire destroyed the cannery structure, and laboratories and research space were built in the 1970s.

PNNL-Sequim researchers cover a number of topics from marine renewable energy to coastal resilience to monitoring the environment.

For more information, visit pnnl.gov/pnnl-sequim.

________

Matthew Nash is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. Reach him at matthew.nash@sequimgazette.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading