Planned closures, repairs of Discovery Trail discussed

PORT ANGELES — Olympic Discovery Trail users were given a mixed bag of good and bad news Tuesday.

City of Port Angeles and Clallam County staff told an audience of about 30 people at City Hall that expansions of the trail will occur over the next few years, but also outlined how portions in Port Angeles will be closed for long periods of time, possibly putting the 2012 Olympic Discovery Marathon in jeopardy.

The major closures will occur in Port Angeles from the former Rayonier mill site to the Red Lion Hotel as the city’s approximately $40 million project to get control of its sewage overflows gets under way.

Glenn Cutler, city public works and utilities director, said that construction will occur during June 2012 — when the marathon, which uses the trail, is under way — and possibly during June 2013.

“I know you probably aren’t going to be able to run a marathon at that point over that location,” he said.

Port Angeles Marathon Association President Larry Little, reached by phone after the meeting, said he couldn’t comment at this time whether the marathon will be able to continue next year or use a detour.

“I don’t want to make any comments without having some more information about what’s going on,” he said.

Marathon OK this year

It won’t be impacted this year.

Kathryn Neal, city engineering manager, said Friday that closures could impact portions of the trail from the former mill site to the hotel anywhere between six months and a year.

Cutler said after the meeting that he didn’t want to comment on the possible duration of the closures since that won’t be fully fleshed out until after a construction contract is awarded this summer.

It’s also not yet known when the closures will start.

Construction will begin sometime after late October at the intersection of Oak Street and Railroad Avenue and at the trail just east of the intersection of Lincoln Street and Railroad Avenue.

At those locations, the city’s contractor will begin “sliplining” new sewer lines into the industrial waterline.

From downtown to the Rayonier site, the city’s plan calls for seven pits to be dug so that crews can continue to pull the pipes through the waterline, which is no longer in use past the Nippon paper mill.

The pipes will connect with a nearly 5-million-gallon tank the city acquired from Rayonier and its wastewater treatment plant nearby.

The tank will temporarily store untreated sewage and storm water when the plant is at capacity, allowing the city to reduce its sewage overflows from anywhere between 30 and 110 a year to slightly over one on average.

On the west side of Port Angeles, an undeveloped portion of the trail will be temporarily closed this year at Milwaukee Drive and 18th Street so that a sewer line from the Lower Elwha Klallam reservation can be connected with the city’s sewers.

That work is expected to start shortly, Cutler said, but he didn’t have a schedule yet from the National Park Service, which is handling that project because it’s intended to replace the tribe’s septic tanks, which are expected to become unusable after Elwha River dams come down beginning in September.

There was also a fair amount of good news.

Storm damage on the trail east of the Rayonier site should be repaired this year, Cutler said.

Also, a new Ennis Creek bridge will be built over the next few years that will reroute the trail away from the treatment plant.

Rich James, Clallam County transportation program manager, said that the northern loop around Lake Crescent should be done in 2012 and that 4,300 feet of trail will be constructed west of the lake this summer.

The city also plans to improve the route the trail takes through downtown as part of its waterfront development plan.

A bridge over Dry Creek in west Port Angeles was opened last month, although the tribe’s sewer line still needs to be placed underneath it.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading