The Elwha River flows past a sign that says “road work ahead” Thursday as crews move rocks to prevent people from driving on the field at the entrance to Olympic National Park. Access to the Elwha Valley will be limited during reconstruction of Olympic Hot Springs Road. (Jesse Major/Peninsula Daily News)

The Elwha River flows past a sign that says “road work ahead” Thursday as crews move rocks to prevent people from driving on the field at the entrance to Olympic National Park. Access to the Elwha Valley will be limited during reconstruction of Olympic Hot Springs Road. (Jesse Major/Peninsula Daily News)

Olympic Hot Springs Road repairs discussed

Could begin in July 2021, be completed by October 2023

OLYMPIC NATIONAL PARK — Restoring long-term vehicle access to Olympic National Park’s Elwha Valley likely will mean multiple several-month-long closures to foot and bicycle traffic to the site of historic Elwha dam removal project over the next few years.

Those who attended a public meeting Wednesday evening, hosted by Olympic National Park and the Federal Highway Administration, learned that construction on Olympic Hot Springs Road — which would include an upland reroute out of the floodplain — could begin in July 2021 and be completed by October 2023.

Kirk Loftsgaarden, project manager for the Federal Highway Administration, said that a Finding of No Significant Impact is expected in March, but stressed that the timeline for the project largely depends on the permitting process.

To complete the project by October 2023 requires the park to follow this “aggressive” timeline, he said, adding that another similar project he worked on took nearly two years to secure a permit after a Finding of No Significant Impact.

“I think this is going to be faster than that, but in the back of our minds we’re well aware that the timeline can go from three months to you name it,” he said.

He said construction would likely last about six months at a time, starting in the spring and ending in the fall. During that time there would not be access from the park entrance.

“Right now we are looking at not having access during construction,” Loftsgaarden said. “That is our thought right now.”

Olympic National Park staff move rocks Thursday to prevent people from driving on a field at the Madison Falls trailhead. (Jesse Major/Peninsula Daily News)

Olympic National Park staff move rocks Thursday to prevent people from driving on a field at the Madison Falls trailhead. (Jesse Major/Peninsula Daily News)

The preferred alternative listed in the Environmental Assessment for the project, which Loftsgaarden said would cost about $8.3 million, calls for rerouting the one-mile section of road afflicted by frequent washouts since the Elwha River was freed from two dams.

The EA is available online at parkplanning.nps.gov/OHSREA. Comments can be submitted online, or mailed or hand-delivered to Olympic National Park, Attn: Superintendent Sarah Creachbaum, Olympic Hot Springs Road Long-Term Access EA, 600 E. Park Ave., Port Angeles, WA 98362.

The park is continuing to accept comments through Dec. 18.

The park has struggled to maintain access to the Elwha Valley via Olympic Hot Springs Road since the completion of the dam removal project in 2014.

The purpose of the project is to rehabilitate the 8.2 mile Olympic Hot Springs Road within Olympic National Park — a project the park has eyed for several years — to ensure public and administrative access to visitor use areas within the Elwha Valley.

The rehabilitated roadway would provide year-round road access to the Elwha Ranger Station and Glines Canyon Spillway Overlook, and seasonal access to Whiskey Bend Road and the upper portion of Olympic Hot Springs Road to Boulder Creek Trailhead.

Once built, the existing 1-mile portion of the roadway, which passes by the former Elwha Campground, would be removed and the area restored.

This option would require cutting trees and adding fill over the length of the reroute, creating risk for increased rock fall and landslides.

Loftsgaarden said the reroute will require adding filling along the slope and, in spots, adding retaining walls. In some areas the walls would cause less disturbance than adding fill.

“Fill is always easier, but it is not always better because it takes up more space,” he said. “It adds more space for things like non-native plants to come in.”

The reroute would also require removal of about 42 to 52 Douglas fir, big leaf maple, western hemlock and western red cedar trees measuring more than 12 inches in diameter. Of those, Loftsgaarden said two to three up to 84 inches in diameter would need to be removed.

Utility poles that line the road to the ranger station would be removed and the utilities would be run underground, he said.

When the park removes the road, it will need to add natural debris in that area, which Loftsgaarden said would allow the river to find a more natural route. Without the debris, the river would likely reroute to the existing route of the road.

“We’ve had a road out there so long and the vegetation is small and maintained, as soon as we remove the road and let the river do its thing, it’s going to go right to where we’ve been driving the past 100 years,” he said. “The idea is to put things out there to discourage that from happening and let it figure out where it wants to go.”

________

Reporter Jesse Major can be reached at 360-452-2345, ext. 56250, or at jmajor@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading