The Western Port Angeles Harbor Group is planning a restoration pilot study that includes placing a 6-inch layer of clean sand on a 4,500-square-foot stretch of shallow subtidal area on the inside of Ediz Hook. (Jesse Major/Peninsula Daily News)​

The Western Port Angeles Harbor Group is planning a restoration pilot study that includes placing a 6-inch layer of clean sand on a 4,500-square-foot stretch of shallow subtidal area on the inside of Ediz Hook. (Jesse Major/Peninsula Daily News)​

Officials hope sand cap layer works as project restoration option at Ediz Hook

PORT ANGELES — Officials are preparing to apply a 6-inch layer of sand to an inside portion of Ediz Hook to test whether a sand cap could be a potential restoration solution.

Commissioners of the Port of Port Angeles, one of five members of the Western Port Angeles Harbor Group, approved the port’s portion of the costs for the project — up to $77,000 — on Tuesday.

“We’re looking at different restoration options and it’s looking like [this] may be a good option on the inside of Ediz Hook,” said Jesse Waknitz, environmental manager for the port.

“Because it’s such a dynamic environment, we want to see if it’s feasible.”

Other members of the group are the city of Port Angeles, Georgia-Pacific LLC, Nippon Paper Industries USA Co. Ltd. and Merrill &Ring, which were identified by the state Department of Ecology as potentially liable parties after pollutants were found in the harbor.

During a 2008 Ecology investigation of the harbor, officials found dioxins, furans, polychlorinated biphenyls, semi-volatile organics such as phenols and phthalates, ammonia and sulfides from decomposing wood debris, and toxic metals such as arsenic, mercury, cadmium and zinc.

Each member of the group is paying 25 percent of the total cost for the project, Waknitz said, except for Nippon and Merrill &Ring, which will pay a combined amount.

To date, all costs to the port associated with this work have been reimbursed by its insurance.

The five parties entered into an agreement with environmental consultant Anchor QEA in December 2013 to provide support and navigate the potential natural resource damage liabilities in Port Angeles Harbor.

The plan is to drop a 6-inch layer of sand on 4,500 square feet of shallow subtidal area where there is wood debris on the inside of Ediz Hook, about 10 feet below sea level.

Monitoring of the cap would begin immediately after construction and would continue through spring 2018.

It would include measuring uniformity and stability of the sand and surveying for invertebrate abundance and sampling of sulfide concentrations in the sand cap.

Waknitz said sand caps have been used in other areas for restoration, but because of how dynamic the harbor is, it isn’t known for sure if the idea will work.

He anticipated work would likely start in May. Work will be overseen by Anchor, which will award the contract, he said.

The data would be summarized in a report that will be used by the Western Port Angeles Harbor Group in future negotiations with the Natural Resource Damage Trustee Council on potential restoration actions.

The city of Port Angeles will be the State Environmental Policy Act lead agency for the proposal and will conduct the required environmental review for the city Shoreline Master Program, according to the port.

Efforts to reach City Manager Dan McKeen on Wednesday were unsuccessful.

The project is expected to require permits and approvals from the U.S. Army Corps of Engineers and the state Department of Fish and Wildlife.

Rebecca Lawson, Ecology’s southwest regional manager, said another aspect is to see whether eelgrass will take to the sand.

She said the plan is to use eelgrass removed during the U.S. Navy’s pier project at Ediz Hook and relocate it to the sand cap.

“The trustee council and Western Port Angeles Harbor Group are trying to take advantage of an opportunity to see if this 6-inch sand layer can be used more extensively as part of restoration work,” she said.

Waknitz said that portion is being done by the Lower Elwha Klallam Tribe and is not part of the Western Port Angeles Harbor Group’s work order.

“It’s an opportunity for us to work together,” he said.

Efforts to reach the tribe were unsuccessful Wednesday.

________

Reporter Jesse Major can be reached at 360-452-2345, ext. 56250, or at jmajor@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading