Numbers vary on turbine electrical generation; intent not power production, Port Angeles city says

Numbers vary on turbine electrical generation; intent not power production, Port Angeles city says

PORT ANGELES — Three wind turbines erected at the city’s Waterfront Park in mid-September that cost $107,516 will generate $1.39 worth of electricity a day and about $42 a month — when they are eventually turned on.

Or they will generate an average of $1.85 a day and $55.59 a month, Nathan West, city community economic and development director, said Tuesday. He said Friday that at peak generation, they would provide $168.63 monthly.

The truth is, city officials don’t really know because they can’t predict wind speeds, West said.

An article last Sunday in the Peninsula Daily News erroneously said the windmill-like turbines, put up in September but not yet in operation, would generate about $1.50 a month.

One reason to build the turbines was that they would illuminate the Waterfront Park lights and feed the remaining electricity back into the Bonneville Power Administration grid, city officials said when they approved the project last year.

But the turbines were not built to only generate electricity, West said Tuesday.

They were built “to ensure we have a vertical element to draw visitors to the park,” he said.

“A great deal went into the design of the park. The design was the predominant focus.

“The purpose was not the generation of electricity.”

Shailesh Shere, city assistant director of power systems, said Friday that the turbines’ output of $1.39 a day and $41.70 a month — an estimated $500 a year — was based on operating at 25 percent of peak usage, generating 18 kilowatt hours a day, with an estimate of prevailing wind speeds of 12 to 14 mph for 24 hours.

But West said a more accurate estimate based on historical wind speeds at William R. Fairchild International Airport would be that the turbines will work at an average of 33 percent of peak usage.

The city pays the Bonneville Power Administration 7.7 cents per kilowatt hour for electricity.

That means they would generate $55.44 monthly and $667.28 a year.

“Approximately 25 percent of the year we historically have enough wind to produce peak generation. The other 75 percent, the spires would produce energy at a reduced rate. For that reason, I am assuming average generation at 33 percent of peak,” West said in an email last week.

The wind spires were to “create a vibrant park that had vertical elements, that had artwork … and also provide examples of alternative energy,” West said Friday.

“The intent was not to provide energy for the grid.”

Shailesh said the lights would use 5.45 kilowatt hours a day from the 18 kilowatt hours a day that would be generated.

The remaining 12.55 kilowatt hours a day would be fed back into the grid, earning the city 12.55 times the prevailing retail rate, Shere said.

Over 25 years, or the depreciable life of the equipment, the city would generate about $24,145 of electrical energy, assuming the electrical rate increases 5 percent a year, Shere said.

The turbines are not in use while the city is involved in an inspection-related dispute with the manufacturer, UGE International Ltd. of New York City, West said.

City officials hope to resolve the impasse by January, he added.

Councilman Lee Whetham said when the city council approved the project in October 2015, it was presented as a way to generate electricity for park lighting.

Money was made available for the turbines when the city received a $285,952 Clallam County Opportunity Fund grant.

Whetham said Wednesday he is “absolutely” concerned that the electricity generated by the turbines will not cover the cost of the project.

“As stewards of taxpayer dollars, we should have questioned staff more on this,” Whetham said.

But he did not regret his vote, he said.

“We continue to leapfrog from one hot-button issue to another.”

Mayor Patrick Downie said he likes the wind turbines on the waterfront.

“We were told the purpose of them was to provide the lighting and security needed” at the park, he said.

“It’s a design element to be introduced down there, and that’s fine in itself.

“Let’s give it a chance.

“As a community, we need to be willing to step out of the box and get out of our comfort zone and say, ‘Let’s be willing to consider other alternative resources like those down there.’”

Councilwoman Sissi Bruch said Thursday had she known the turbines were so inefficient, she would have asked city staff to do more research to find a more efficient design.

“I regret the specific design, not the overall turbines,” she said.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at paul.gottlieb@peninsuladailynews.com.

More in News

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading

Workers from Van Ness Construction in Port Hadlock, one holding a grade rod with a laser pointer, left, and another driving the backhoe, scrape dirt for a new sidewalk of civic improvements at Walker and Washington streets in Port Townsend on Thursday. The sidewalks will be poured in early February and extend down the hill on Washington Street and along Walker Street next to the pickle ball courts. (Steve Mullensky/for Peninsula Daily News)
Sidewalk setup

Workers from Van Ness Construction in Port Hadlock, one holding a grade… Continue reading