Nippon biomass cogeneration plant targets Nov. 1 start

PORT ANGELES — Work could wrap up in the next several weeks on Nippon Paper Industries USA’s long-stalled biomass cogeneration plant.

The expectation is that it will be up and running full bore by Nov. 1.

“We hope to beat that,” Steve Johnson, mill manager, said last week. “We have several weeks of work left.”

Tests on the new boiler mud drum that was installed in early September will result in a steam plume expected to issue from the plant at Ediz Hook later this week, Johnson said.

If the Nov. 1 finish date holds, the cogeneration plant will be fully operational nearly a year after the project was slated to begin producing steam for the mill and 20 megawatts of electricity for the mill and for sale to buyers of green energy.

The Tokyo-based company had made agreements with buyers who wanted to purchase the cogeneration plant’s electricity.

Nippon has made good on the commitments by purchasing electricity on its own and reselling it to those buyers.

“We did what was right by our customers,” Johnson said.

“We made a commitment, and we honored it.”

The project, expected to exceed $85 million, was dedicated during a ceremony at the papermaking plant Nov. 1, 2013, with the expectation is would be operational later

that month.

But cracks were discovered in the plant boiler’s mud drum, a 30-foot, 25-ton pressurized vessel that collects solids from the boiler drum, and the plant has never operated at capacity.

The mud drum and 40,000 feet of tubing have since been replaced in repairs that have boosted the cost of the project, which had been estimated at $71 million in 2010 and rose 20 percent to $85 million by 2013.

Johnson would not disclose the current cost but said it will be “comfortably” under $90 million.

The project upgrades the existing cogeneration plant, which has an antiquated boiler that uses biomass — woody debris such as forest slash and peeled bark — to produce only steam for the plant and is in use until the new boiler works.

Nippon, which produces telephone book paper and newsprint for the Peninsula Daily News and the weekly Sequim Gazette and Forks Forum, continues to employ about 200 workers and operate 24 hours a day, seven days a week, Johnson said.

“The support out of Tokyo and senior management has been outstanding,” he added.

“Certainly they’re disappointed in the delays, don’t get me wrong, but their support has been strong.”

Problems with the biomass plant first shut it down completely in February.

Nippon and Covington, La.-based FSE Energy, the primary contractor for the cogeneration plant project, expect to undergo mediation to determine who will cover repair and replacement costs, Johnson said.

“We’re still waiting on the contractor to get back to us, and we can meet in mediation,” he said.

Earlier this summer, a hole was cut in the side of the boiler and the cracked mud drum rolled out on a steel jig before being placed on the ground.

The new mud drum “went in exactly the same way” the old component came out, Johnson said.

On Sept. 8, the boiler was filled with water, pressure was applied, and their were no leaks.

The boiler can produce 225,000 pounds of steam.

“There are still many weeks to go, but it was a big milestone, if you will,” Johnson said.

The boiler wall was replaced the weekend of Sept. 13, and the internal surface was chemically cleaned by Friday.

Port Townsend Paper Corp. earlier this year abandoned a much-disputed $54 million project to upgrade its own cogeneration plant that would have generated 24 megawatts.

Both projects survived numerous environmental challenges.

But those challenges slowed down the Port Townsend project and, combined with a strong market for cheap natural gas, were a factor in dooming it, company President Roger Hagan told Peninsula Daily News earlier this year.

The cracked mud drum and 1,600 steam tubes from Nippon’s cogeneration project will remain in the mill’s parking lot for the time being.

“We’re obviously saving those for arbitration,” Johnson said.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at pgottlieb@peninsuladailynews.com.

More in News

Crews work to remove metal siding on the north side of Field Arts & Events Hall on Thursday in Port Angeles. The siding is being removed so it can be replaced. (Dave Logan/for Peninsula Daily News)
Siding to be replaced

Crews work to remove metal siding on the north side of Field… Continue reading

Tsunami study provides advice

Results to be discussed on Jan. 20 at Field Hall

Chef Arran Stark speaks with attendees as they eat ratatouille — mixed roasted vegetables and roasted delicata squash — that he prepared in his cooking with vegetables class. (Elijah Sussman/Peninsula Daily News)
Nonprofit school is cooking at fairgrounds

Remaining lectures to cover how to prepare salmon and chicken

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects

Olympic Medical Center Board President Ann Henninger, left, recognizes commissioner Jean Hordyk on Wednesday as she steps down after 30 years on the board. Hordyk, who was first elected in 1995, was honored during the meeting. (Paula Hunt/Peninsula Daily News)
OMC Commissioners to start recording meetings

Video, audio to be available online

Jefferson PUD plans to keep Sims Way project overhead

Cost significantly reduced in joint effort with port, city

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park