Nippon biomass cogeneration plant targets Nov. 1 start

PORT ANGELES — Work could wrap up in the next several weeks on Nippon Paper Industries USA’s long-stalled biomass cogeneration plant.

The expectation is that it will be up and running full bore by Nov. 1.

“We hope to beat that,” Steve Johnson, mill manager, said last week. “We have several weeks of work left.”

Tests on the new boiler mud drum that was installed in early September will result in a steam plume expected to issue from the plant at Ediz Hook later this week, Johnson said.

If the Nov. 1 finish date holds, the cogeneration plant will be fully operational nearly a year after the project was slated to begin producing steam for the mill and 20 megawatts of electricity for the mill and for sale to buyers of green energy.

The Tokyo-based company had made agreements with buyers who wanted to purchase the cogeneration plant’s electricity.

Nippon has made good on the commitments by purchasing electricity on its own and reselling it to those buyers.

“We did what was right by our customers,” Johnson said.

“We made a commitment, and we honored it.”

The project, expected to exceed $85 million, was dedicated during a ceremony at the papermaking plant Nov. 1, 2013, with the expectation is would be operational later

that month.

But cracks were discovered in the plant boiler’s mud drum, a 30-foot, 25-ton pressurized vessel that collects solids from the boiler drum, and the plant has never operated at capacity.

The mud drum and 40,000 feet of tubing have since been replaced in repairs that have boosted the cost of the project, which had been estimated at $71 million in 2010 and rose 20 percent to $85 million by 2013.

Johnson would not disclose the current cost but said it will be “comfortably” under $90 million.

The project upgrades the existing cogeneration plant, which has an antiquated boiler that uses biomass — woody debris such as forest slash and peeled bark — to produce only steam for the plant and is in use until the new boiler works.

Nippon, which produces telephone book paper and newsprint for the Peninsula Daily News and the weekly Sequim Gazette and Forks Forum, continues to employ about 200 workers and operate 24 hours a day, seven days a week, Johnson said.

“The support out of Tokyo and senior management has been outstanding,” he added.

“Certainly they’re disappointed in the delays, don’t get me wrong, but their support has been strong.”

Problems with the biomass plant first shut it down completely in February.

Nippon and Covington, La.-based FSE Energy, the primary contractor for the cogeneration plant project, expect to undergo mediation to determine who will cover repair and replacement costs, Johnson said.

“We’re still waiting on the contractor to get back to us, and we can meet in mediation,” he said.

Earlier this summer, a hole was cut in the side of the boiler and the cracked mud drum rolled out on a steel jig before being placed on the ground.

The new mud drum “went in exactly the same way” the old component came out, Johnson said.

On Sept. 8, the boiler was filled with water, pressure was applied, and their were no leaks.

The boiler can produce 225,000 pounds of steam.

“There are still many weeks to go, but it was a big milestone, if you will,” Johnson said.

The boiler wall was replaced the weekend of Sept. 13, and the internal surface was chemically cleaned by Friday.

Port Townsend Paper Corp. earlier this year abandoned a much-disputed $54 million project to upgrade its own cogeneration plant that would have generated 24 megawatts.

Both projects survived numerous environmental challenges.

But those challenges slowed down the Port Townsend project and, combined with a strong market for cheap natural gas, were a factor in dooming it, company President Roger Hagan told Peninsula Daily News earlier this year.

The cracked mud drum and 1,600 steam tubes from Nippon’s cogeneration project will remain in the mill’s parking lot for the time being.

“We’re obviously saving those for arbitration,” Johnson said.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at pgottlieb@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading