Nippon biomass cogeneration plant remains offline; Port Angeles facility slated to undergo repairs starting in September

PORT ANGELES — Nippon Paper Industries USA’s upgraded $85 million biomass cogeneration plant, which has not been fully operational since it was dedicated in November, continues to be shut down and will undergo major surgery this fall.

The new facility’s mud drum, a water-pressurized main component of the new boiler, and 1,560 pieces of piping will be replaced beginning in September, mill manager Steve Johnson said Wednesday, predicting the new facility should be up and running by October.

“We don’t know how much the final cost is going to be, but it will be substantial,” Johnson said.

“It will be what it is to make it right.”

Nippon’s aging No. 8 boiler, which will be replaced by the new boiler, has been upgraded and is providing steam for the factory without any slowdowns, Johnson said.

That’s allowed Nippon to continue manufacturing paper for telephone books and newspapers, including the Peninsula Daily News, 24 hours a day with a fully staffed workforce of about 220 employees, he said.

Like the No. 8 boiler, the cogeneration plant will create steam for the plant by burning biomass, or woody debris such as forest slash and peeled bark.

But unlike No. 8, the new boiler will generate 20 megawatts of electricity for sale as green energy.

Port Townsend Paper Corp.’s $54 million project to upgrade its own cogeneration plant and produce up to 24 megawatts was abandoned earlier this year by company officials who blamed environmental challenges and inexpensive natural gas for dooming the effort.

The cost of Nippon’s project rose from an estimated $71 million in 2010 to $85 million by the time Nippon officials from the company’s Japanese home base toasted the new facility during elaborate dedication ceremonies in November.

The cogeneration plant, which has never been up and running full bore, shut down completely March 11 after cracks were discovered in the 25-ton, 30-foot-long mud drum, he said.

The mill had stopped producing paper for two weeks beginning in February for a maintenance shutdown that had been moved ahead of schedule.

The cracks were discovered after the mill started up again and water-pressure tests were conducted on the mud drum to see whether there were any leaks.

“That’s when we found the cracks,” Johnson said.

The Nippon and Port Townsend Paper Corp. projects survived numerous legal challenges from environmental groups.

Nippon is now faced with potential legal challenges of a contractual nature.

Lawyers for Nippon and Covington, La.-based FSE Energy, which built the boiler, are communicating over who is responsible for fixing the boiler — and who will pay — but no civil action has been filed by either party, Johnson said.

“We are at the beginning of the process of dispute resolution,” he said.

“They felt it was something we did in the operation of the boiler that caused the cracking. We strongly disagreed.

“We feel they have some responsibility; they feel they have none,” Johnson continued.

“With that, we are working through arbitration and mediation.

“Until that’s all done, it’s a very delicate situation.”

Bo Thibaut, CEO of FSE Energy, did not return calls for comment Wednesday.

Jim Thibaut, Bo’s father and founder of the company, has “personally delivered over 75 turn-key boiler projects,” according to the company’s website, www.fseenergy.com.

With FSE vacating the site “at their doing,” Nippon has hired Portland, Ore.-based CH Murphy Clark Ullman Inc. to build a new boiler, Johnson said.

The 50,000-pound forged steel mud drum is encased inside the boiler.

Workers will cut a hole in the side of the boiler, put the mud drum on rails and roll it out through the side of the boiler building, “not unlike taking a roll out of the paper machine,” Johnson said.

Nippon has signed contracts to sell electricity generated by the cogeneration plant that remain in effect, Johnson said.

The company began purchasing green power for those customers from other sources “a few weeks ago” to keep those contracts valid, he added.

Johnson would not comment how much that power is costing Nippon but characterized the financial impact as “painful.”

“We should be up and running and supplying that power,” he said.

“It’s hard to accept.”

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at pgottlieb@peninsuladailynews.com.

More in News

Two dead after tree falls in Olympic National Forest

Two women died after a tree fell in Olympic National… Continue reading

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend, volunteer at the Martin Luther King Day of Service beach restoration on Monday at Fort Worden State Park. The activity took place on Knapp Circle near the Point Wilson Lighthouse. Sixty-four volunteers participated in the removal of non-native beach grasses. (Steve Mullensky/for Peninsula Daily News)
Work party

Sue Long, left, Vicki Bennett and Frank Handler, all from Port Townsend,… Continue reading

Portion of bridge to be replaced

Tribe: Wooden truss at railroad park deteriorating

Kingsya Omega, left, and Ben Wilson settle into a hand-holding exercise. (Aliko Weste)
Process undermines ‘Black brute’ narrative

Port Townsend company’s second film shot in Hawaii

Jefferson PUD to replace water main in Coyle

Jefferson PUD commissioners awarded a $1.3 million construction contract… Continue reading

Scott Mauk.
Chimacum superintendent receives national award

Chimacum School District Superintendent Scott Mauk has received the National… Continue reading

Hood Canal Coordinating Council meeting canceled

The annual meeting of the Hood Canal Coordinating Council, scheduled… Continue reading

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the rotunda of the old Clallam County Courthouse on Friday in Port Angeles. The North Olympic History Center exhibit tells the story of the post office past and present across Clallam County. The display will be open until early February, when it will be relocated to the Sequim City Hall followed by stops on the West End. The project was made possible due to a grant from the Clallam County Heritage Advisory Board. (Dave Logan/for Peninsula Daily News)
Post office past and present

Bruce Murray, left, and Ralph Parsons hang a cloth exhibition in the… Continue reading

This agave grew from the size of a baseball in the 1990s to the height of Isobel Johnston’s roof in 2020. She saw it bloom in 2023. Following her death last year, Clallam County Fire District 3 commissioners, who purchased the property on Fifth Avenue in 2015, agreed to sell it to support the building of a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group file)
Fire district to sell property known for its Sequim agave plant

Sale proceeds may support new Carlsborg station project

As part of Olympic Theatre Arts’ energy renovation upgrade project, new lighting has been installed, including on the Elaine and Robert Caldwell Main Stage that allows for new and improved effects. (Olympic Theatre Arts)
Olympic Theatre Arts remodels its building

New roof, LED lights, HVAC throughout

Weekly flight operations scheduled

Field carrier landing practice operations will be conducted for aircraft… Continue reading